55 09th St
San Francisco permit 201108233049 · South of Market
To erect 17 stories, 273 units residential, retail & parking building.
- Filed
- Aug 23, 2011
- Issued
- Jun 25, 2012 (10 months after filing)
- Completed
- Oct 14, 2014 (28 months after issuance)
- Review stops
- 77 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 19 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 24, 2011 | Aug 24, 2011 | — |
Zoning review Planning · CP-ZOC | Aug 24, 2011 | Feb 13, 2012 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2011 | Jun 4, 2012 | — |
Building plan review Building Inspection · BLDG | Feb 15, 2012 | Apr 27, 2012 | — |
Fire prevention review Fire Department · SFFD | Feb 16, 2012 | Apr 30, 2012 | — |
Transportation (SFMTA) review MTA · SFMTA | Mar 27, 2012 | Mar 29, 2012 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 30, 2012 | May 15, 2012 | — |
Street use and mapping Public Works · DPW-BSM | Apr 17, 2012 | May 11, 2012 | — |
Zoning review Planning · CP-ZOC | May 17, 2012 | Jun 1, 2012 | — |
Development fee collection Building Inspection · DFCU | Jun 4, 2012 | Jun 19, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2012 | Jun 25, 2012 | — |
Addendum 1: Foundation-level one
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2012 | Mar 7, 2012 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2012 | Jun 15, 2012 | — |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2012 | Jun 20, 2012 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2012 | Jul 2, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2012 | Jul 3, 2012 | — |
Addendum 2: Architectural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 26, 2012 | Jun 26, 2012 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2012 | Aug 28, 2012 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2012 | Oct 26, 2012 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 30, 2012 | Nov 20, 2012 | — |
Fire prevention review Fire Department · SFFD | Aug 31, 2012 | Nov 28, 2012 | — |
Street use and mapping Public Works · DPW-BSM | Sep 10, 2012 | Dec 14, 2012 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2012 | Sep 21, 2012 | — |
Building plan review Building Inspection · BLDG | Nov 15, 2012 | Nov 15, 2012 | — |
Zoning review Planning · CP-ZOC | Nov 28, 2012 | Dec 12, 2012 | — |
Permit Processing Center Building Inspection · PPC | Dec 17, 2012 | Dec 19, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Dec 19, 2012 | Dec 19, 2012 | — |
Addendum 3: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building plan review Building Inspection · BLDG | Jun 26, 2012 | Aug 31, 2012 | — |
Fire prevention review Fire Department · SFFD | Jun 26, 2012 | Jul 1, 2012 | — |
Permit Processing Center Building Inspection · PPC | Aug 31, 2012 | Aug 31, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2012 | Sep 4, 2012 | — |
Addendum 4: Air replenishment
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 27, 2012 | Sep 27, 2012 | — |
Building plan review Building Inspection · BLDG | Sep 27, 2012 | Oct 3, 2012 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2012 | Nov 5, 2012 | — |
Fire prevention review Fire Department · SFFD | Nov 5, 2012 | Jan 11, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jan 11, 2013 | Jan 11, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Jan 11, 2013 | Jan 15, 2013 | — |
Addendum 5: Mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2013 | May 3, 2013 | — |
Building plan review Building Inspection · BLDG | May 3, 2013 | May 7, 2013 | — |
Fire prevention review Fire Department · SFFD | May 4, 2013 | Nov 8, 2013 | — |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2013 | Dec 2, 2013 | — |
Building plan review Building Inspection · BLDG | Dec 2, 2013 | Dec 3, 2013 | — |
Permit Processing Center Building Inspection · PPC | Dec 3, 2013 | Dec 3, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2013 | Dec 5, 2013 | — |
Addendum 6: Fire service elevator
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 19, 2013 | Nov 19, 2013 | — |
Fire prevention review Fire Department · SFFD | Nov 19, 2013 | Dec 31, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jan 2, 2014 | Jan 2, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2014 | Jan 2, 2014 | — |
Addendum 7: Fire sprinklers, standpipes, underground and fire pump.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 4, 2012 | Dec 4, 2012 | — |
Fire prevention review Fire Department · SFFD | Dec 4, 2012 | May 29, 2013 | — |
Structural plan approval Building Inspection · PAD-STR | May 31, 2013 | Jun 10, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jun 11, 2013 | Jun 13, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2013 | Jun 13, 2013 | — |
Addendum 8: Stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 28, 2013 | Jan 28, 2013 | — |
Building plan review Building Inspection · BLDG | Jan 28, 2013 | Feb 15, 2013 | — |
Permit Processing Center Building Inspection · PPC | Feb 15, 2013 | Feb 19, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Feb 19, 2013 | Feb 21, 2013 | — |
Addendum 9: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 28, 2013 | Jan 28, 2013 | — |
Fire prevention review Fire Department · SFFD | Jan 28, 2013 | Dec 5, 2013 | — |
Permit Processing Center Building Inspection · PPC | Dec 5, 2013 | Dec 5, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Dec 5, 2013 | Dec 6, 2013 | — |
Addendum 10: Exterior curtain wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 28, 2013 | Feb 28, 2013 | — |
Zoning review Planning · CP-ZOC | Feb 28, 2013 | Apr 3, 2013 | — |
Building plan review Building Inspection · BLDG | Apr 4, 2013 | Apr 23, 2013 | — |
Fire prevention review Fire Department · SFFD | Apr 24, 2013 | Jun 2, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jun 3, 2013 | Jun 3, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2013 | Jun 3, 2013 | — |
Addendum 11: Fuel oil generator
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 30, 2013 | Aug 30, 2013 | — |
Building plan review Building Inspection · BLDG | Aug 30, 2013 | Oct 30, 2013 | — |
Fire prevention review Fire Department · SFFD | Sep 5, 2013 | Dec 11, 2013 | — |
Building plan review Building Inspection · BLDG | Dec 12, 2013 | Dec 12, 2013 | — |
Permit Processing Center Building Inspection · PPC | Dec 12, 2013 | Dec 12, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2013 | Dec 13, 2013 | — |
Addendum 12: Errc system (new)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 13, 2013 | Nov 13, 2013 | — |
Fire prevention review Fire Department · SFFD | Nov 13, 2013 | Jan 16, 2014 | — |
Permit Processing Center Building Inspection · PPC | Jan 16, 2014 | Jan 16, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Jan 16, 2014 | Jan 16, 2014 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $84,965,000
| Name | Role | License on permit |
|---|---|---|
| Ronald Klemencic Magnusson Klemencic Assoc. | Engineer | 4477 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026