209 Prentiss St
San Francisco permit 201112090432 · Bernal Heights
Erect 3 story single family residential.
- Filed
- Dec 9, 2011
- Issued
- Mar 19, 2015 (39 months after filing)
- Completed
- Jul 17, 2020 (64 months after issuance)
- Review stops
- 27 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 13, 2011 | Dec 13, 2011 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2011 | May 23, 2014 | — |
Planning neighborhood notice Planning · CP-NP | Dec 14, 2011 | Jun 21, 2012 | — |
Building plan review Building Inspection · BLDG | May 30, 2014 | Jul 11, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2014 | Jul 18, 2014 | — |
Fire prevention review Fire Department · SFFD | Jun 20, 2014 | Aug 1, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2014 | Jul 16, 2014 | — |
Fire prevention review Fire Department · SFFD | Aug 1, 2014 | Aug 1, 2014 | — |
Zoning review Planning · CP-ZOC | Aug 11, 2014 | Aug 14, 2014 | — |
Permit Processing Center Building Inspection · PPC | Aug 19, 2014 | Aug 19, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2014 | Mar 19, 2015 | — |
Addendum 1: Foundation & super structure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 9, 2015 | Oct 9, 2015 | — |
Building plan review Building Inspection · BLDG | Oct 9, 2015 | Oct 29, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2015 | Nov 4, 2015 | — |
Permit Processing Center Building Inspection · PPC | Nov 5, 2015 | Nov 6, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Nov 6, 2015 | Nov 9, 2015 | — |
Addendum 2: Arch, mech, t-24.final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2016 | Mar 9, 2016 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2016 | May 10, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | May 11, 2016 | Jun 23, 2016 | — |
Fire prevention review Fire Department · SFFD | Jun 6, 2016 | Jun 6, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2016 | Jun 13, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jun 14, 2016 | Jun 22, 2016 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2016 | Jul 12, 2016 | — |
Zoning review Planning · CP-ZOC | Jul 13, 2016 | Jul 15, 2016 | — |
Permit Processing Center Building Inspection · PPC | Jul 18, 2016 | Aug 4, 2016 | — |
Building plan review Building Inspection · BLDG | Aug 2, 2016 | Aug 3, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Aug 4, 2016 | Aug 11, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $313,000
| Name | Role | License on permit |
|---|---|---|
| Winnie Hing-Wan Tam Winnie Tam | Architect | C31166 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025