166 Geary St
San Francisco permit 201201192567 · Financial District/South Beach
Build out of (n) canopy, re-cladding of (e) storefront and replacing of existing entry doors . entry doors to be replaced in-kind. canopy will not block any fire escape, rescue window, or exit. additional permits to be submitted for interior work.
- Filed
- Jan 19, 2012
- Issued
- May 1, 2012 (3 months after filing)
- Completed
- Jun 21, 2012 (2 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Fire prevention review Fire Department · SFFD | Jan 20, 2012 | Jan 20, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Jan 20, 2012 | Jan 20, 2012 | — |
Zoning review Planning · CP-ZOC | Jan 23, 2012 | Mar 21, 2012 | — |
Building plan review Building Inspection · BLDG | Mar 27, 2012 | Mar 27, 2012 | — |
Zoning review Planning · CP-ZOC | Apr 3, 2012 | Apr 4, 2012 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2012 | Apr 12, 2012 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 12, 2012 | Apr 12, 2012 | — |
Permit Processing Center Building Inspection · PPC | Apr 12, 2012 | Apr 12, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Apr 12, 2012 | Apr 13, 2012 | — |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2012 | Apr 17, 2012 | — |
Permit Processing Center Building Inspection · PPC | Apr 18, 2012 | Apr 18, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2012 | May 1, 2012 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Louis Loria Atmosphere | Architect | C-31289 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025