1351 Polk St
San Francisco permit 201203216524 · Nob Hill
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Revision to appl #2012.01.04.1705 - milden damaged sheetrock replaced, bar floors resurfaced, bar counter repaired per health code violatios #3,4,5 on report.
- Filed
- Mar 21, 2012
- Issued
- Mar 23, 2012 (within 1 month of filing)
- Completed
- May 25, 2012 (2 months after issuance)
- Review stops
- 5 stops across 3 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 21, 2012 | Mar 21, 2012 | — |
Building plan review Building Inspection · BLDG | Mar 21, 2012 | Mar 21, 2012 | — |
Fire prevention review Fire Department · SFFD | Mar 21, 2012 | Mar 21, 2012 | — |
Public health review Public Health · HEALTH | Mar 22, 2012 | Mar 22, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2012 | Mar 23, 2012 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $2,000
| Name | Role | License on permit |
|---|---|---|
| Kevin Kramer K K Engineering | Engineer | C54780 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026