260 08th Av
San Francisco permit 201204248965 · Inner Richmond
Remodel bathrooms on 2nd floor, relocate kitchen in both units. add one master bath on third floor. remove portion of load bearing wall on third floor. replace windowsw in kind (19 each on 2nd floor and 3rd floor), in the rear of units, not visible from the street.
- Filed
- Apr 24, 2012
- Issued
- May 7, 2012 (within 1 month of filing)
- Completed
- Nov 15, 2012 (6 months after issuance)
- Review stops
- 5 stops across 2 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 24, 2012 | Apr 24, 2012 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 24, 2012 | Apr 24, 2012 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2012 | Apr 24, 2012 | — |
Building plan review Building Inspection · BLDG | Apr 30, 2012 | Apr 30, 2012 | — |
Central Permit Bureau Building Inspection · CPB | May 7, 2012 | May 7, 2012 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $68,000
| Name | Role | License on permit |
|---|---|---|
| Jason Robert Phoen | Engineer | C57553 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025