23 Clifford Tr
San Francisco permit 201207033978 · Castro/Upper Market
Remodel 2-story, 2-unit building & add (n) 3rd fl.
- Filed
- Jul 3, 2012
- Issued
- Jul 18, 2013 (12 months after filing)
- Completed
- Jul 6, 2017 (48 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 13, 2012 | Jul 13, 2012 | — |
Zoning review Planning · CP-ZOC | Jul 13, 2012 | May 3, 2013 | — |
Planning neighborhood notice Planning · CP-NP | Nov 8, 2012 | Dec 26, 2012 | — |
Building plan review Building Inspection · BLDG | May 6, 2013 | Jul 8, 2013 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2013 | May 16, 2013 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 17, 2013 | Jun 21, 2013 | — |
Zoning review Planning · CP-ZOC | Jun 24, 2013 | Jun 26, 2013 | — |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2013 | Jul 1, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jul 1, 2013 | Jul 1, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2013 | Jul 18, 2013 | — |
Addendum 1: Struct,arch,foundation,steel frame,t24, calc
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 16, 2014 | Jan 16, 2014 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 16, 2014 | Apr 18, 2014 | — |
Building plan review Building Inspection · BLDG | Jan 16, 2014 | May 5, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 18, 2014 | Mar 20, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2014 | May 7, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2014 | May 5, 2014 | — |
Permit Processing Center Building Inspection · PPC | May 8, 2014 | May 8, 2014 | — |
Central Permit Bureau Building Inspection · CPB | May 8, 2014 | Jun 5, 2014 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,100,000
| Name | Role | License on permit |
|---|---|---|
| Joshua W Aidlin Aidlin Darling Design | Architect | C28109 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025