690 Long Bridge St
San Francisco permit 201207054130 · Mission Bay
To erect 16 stories, 273 units apartments & parking building.
- Filed
- Jul 5, 2012
- Issued
- Feb 19, 2013 (8 months after filing)
- Completed
- Dec 11, 2015 (34 months after issuance)
- Review stops
- 92 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 14 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 6, 2012 | Jul 6, 2012 | — |
Redevelopment review Redevelopment · REDEV | Jul 6, 2012 | Oct 11, 2012 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2012 | Sep 10, 2012 | — |
Fire prevention review Fire Department · SFFD | Jul 6, 2012 | Sep 10, 2012 | — |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2012 | Sep 14, 2012 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2012 | Oct 16, 2012 | — |
Permit Processing Center Building Inspection · PPC | Oct 12, 2012 | Oct 12, 2012 | — |
Development fee collection Building Inspection · DFCU | Oct 12, 2012 | Oct 12, 2012 | — |
Central Permit Bureau Building Inspection · CPB | Oct 12, 2012 | Feb 19, 2013 | — |
Addendum 1: Piles & foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building plan review Building Inspection · BLDG | Feb 20, 2013 | Mar 18, 2013 | — |
Street use and mapping Public Works · DPW-BSM | Mar 1, 2013 | Mar 25, 2013 | — |
Redevelopment review Redevelopment · REDEV | Mar 25, 2013 | Mar 28, 2013 | — |
Permit Processing Center Building Inspection · PPC | Mar 28, 2013 | Mar 28, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2013 | Mar 28, 2013 | — |
Addendum 2: Super structure - concrete
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 11, 2013 | Jun 11, 2013 | — |
Building plan review Building Inspection · BLDG | Jun 11, 2013 | Jul 3, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jul 3, 2013 | Jul 3, 2013 | — |
Redevelopment review Redevelopment · REDEV | Jul 30, 2013 | Jul 30, 2013 | — |
Permit Processing Center Building Inspection · PPC | Jul 31, 2013 | Jul 31, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2013 | Jul 31, 2013 | — |
Addendum 3: Super structure - wood
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 9, 2013 | Aug 9, 2013 | — |
Building plan review Building Inspection · BLDG | Aug 9, 2013 | Sep 13, 2013 | — |
Redevelopment review Redevelopment · REDEV | Sep 13, 2013 | Oct 2, 2013 | — |
Permit Processing Center Building Inspection · PPC | Oct 3, 2013 | Oct 3, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2013 | Oct 3, 2013 | — |
Addendum 4: Architectural / m.e.p.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 20, 2013 | Sep 20, 2013 | — |
Building plan review Building Inspection · BLDG | Sep 20, 2013 | Jan 28, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2013 | Feb 26, 2014 | — |
Fire prevention review Fire Department · SFFD | Sep 20, 2013 | Jan 17, 2014 | — |
Redevelopment review Redevelopment · REDEV | Oct 2, 2013 | Oct 2, 2013 | — |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2013 | Apr 18, 2014 | — |
Fire prevention review Fire Department · SFFD | Jan 17, 2014 | Mar 5, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2014 | Feb 28, 2014 | — |
Redevelopment review Redevelopment · REDEV | Mar 12, 2014 | Apr 15, 2014 | — |
Permit Processing Center Building Inspection · PPC | Apr 18, 2014 | Apr 18, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2014 | Apr 18, 2014 | — |
Addendum 5: Curtain wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 18, 2014 | Jun 18, 2014 | — |
Building plan review Building Inspection · BLDG | Jun 18, 2014 | Feb 12, 2015 | — |
Fire prevention review Fire Department · SFFD | Jun 24, 2014 | Oct 16, 2014 | — |
Redevelopment review Redevelopment · REDEV | Feb 12, 2015 | Feb 19, 2015 | — |
Permit Processing Center Building Inspection · PPC | Feb 20, 2015 | Feb 20, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Feb 20, 2015 | Feb 23, 2015 | — |
Addendum 6: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 2, 2014 | Apr 2, 2014 | — |
Fire prevention review Fire Department · SFFD | Apr 2, 2014 | Apr 8, 2014 | — |
Fire prevention review Fire Department · SFFD | Apr 8, 2014 | Jul 22, 2014 | — |
Permit Processing Center Building Inspection · PPC | Jul 23, 2014 | Jul 23, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2014 | Jul 24, 2014 | — |
Addendum 7: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 22, 2014 | Sep 22, 2014 | — |
Fire prevention review Fire Department · SFFD | Sep 22, 2014 | Jan 21, 2015 | — |
Permit Processing Center Building Inspection · PPC | Jan 21, 2015 | Jan 21, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Jan 21, 2015 | Jan 22, 2015 | — |
Addendum 8: Generator / fuel oil / piping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 30, 2015 | Mar 30, 2015 | — |
Building plan review Building Inspection · BLDG | Mar 31, 2015 | Apr 13, 2015 | — |
Fire prevention review Fire Department · SFFD | Apr 3, 2015 | Apr 4, 2015 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2015 | Apr 20, 2015 | — |
Public health review Public Health · HEALTH | Apr 20, 2015 | Apr 23, 2015 | — |
Permit Processing Center Building Inspection · PPC | Apr 23, 2015 | Apr 23, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2015 | Apr 28, 2015 | — |
Addendum 9: Emergency radio system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 3, 2014 | Sep 3, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 3, 2014 | Sep 29, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2015 | Feb 26, 2015 | — |
Fire prevention review Fire Department · SFFD | Feb 26, 2015 | Mar 31, 2015 | — |
Permit Processing Center Building Inspection · PPC | Apr 1, 2015 | Apr 1, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2015 | Apr 1, 2015 | — |
Addendum 10: Stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 22, 2014 | Apr 22, 2014 | — |
Building plan review Building Inspection · BLDG | Apr 22, 2014 | May 23, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2014 | May 8, 2014 | — |
Fire prevention review Fire Department · SFFD | May 9, 2014 | May 29, 2014 | — |
Permit Processing Center Building Inspection · PPC | May 29, 2014 | May 29, 2014 | — |
Central Permit Bureau Building Inspection · CPB | May 29, 2014 | Jun 3, 2014 | — |
Addendum 11: Roof truss system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 3, 2014 | Jun 3, 2014 | — |
Building plan review Building Inspection · BLDG | Jun 3, 2014 | Jul 23, 2014 | — |
Permit Processing Center Building Inspection · PPC | Jul 23, 2014 | Jul 23, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2014 | Jul 24, 2014 | — |
Addendum 12: Landscaping/lighting/common area improve
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2014 | Nov 12, 2014 | — |
Building plan review Building Inspection · BLDG | Nov 12, 2014 | Nov 14, 2014 | — |
Fire prevention review Fire Department · SFFD | Nov 14, 2014 | Nov 24, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Nov 24, 2014 | Nov 26, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 1, 2014 | Dec 2, 2014 | — |
Redevelopment review Redevelopment · REDEV | Dec 2, 2014 | Dec 3, 2014 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2015 | Mar 10, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2015 | Mar 17, 2015 | — |
Addendum 13: Elevator landing two-way communication system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 24, 2014 | Dec 24, 2014 | — |
Building plan review Building Inspection · BLDG | Dec 24, 2014 | Dec 29, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2014 | Jan 14, 2015 | — |
Fire prevention review Fire Department · SFFD | Jan 14, 2015 | Feb 3, 2015 | — |
Permit Processing Center Building Inspection · PPC | Feb 3, 2015 | Feb 3, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2015 | Feb 20, 2015 | — |
Addendum 14: Fire service access elevator (fsae)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 8, 2015 | Apr 8, 2015 | — |
Fire prevention review Fire Department · SFFD | Apr 8, 2015 | May 6, 2015 | — |
Permit Processing Center Building Inspection · PPC | May 6, 2015 | May 6, 2015 | — |
Central Permit Bureau Building Inspection · CPB | May 6, 2015 | May 7, 2015 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $92,000,000
| Name | Role | License on permit |
|---|---|---|
| Jeffrey W Richardson Hks Architects | Architect | C29033 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026