18 Whitney St
San Francisco permit 201308093970 · Glen Park
Horiz. rear yard addition on 3 levels, with renovations to (e) bldg add 2 bathrms, remodel 1 bathrm, relocate 1/2 bath. rear yard deck and stairs, add 2 bedrms, new kitchen
- Filed
- Aug 9, 2013
- Issued
- Mar 18, 2014 (7 months after filing)
- Completed
- Jul 6, 2015 (16 months after issuance)
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 9, 2013 | Aug 9, 2013 | — |
Zoning review Planning · CP-ZOC | Aug 9, 2013 | Jan 22, 2014 | — |
Planning neighborhood notice Planning · CP-NP | Dec 5, 2013 | Dec 11, 2013 | — |
Building plan review Building Inspection · BLDG | Jan 23, 2014 | Feb 24, 2014 | — |
Zoning review Planning · CP-ZOC | Feb 13, 2014 | Feb 21, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2014 | Feb 25, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2014 | Mar 11, 2014 | — |
Permit Processing Center Building Inspection · PPC | Mar 11, 2014 | Mar 11, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2014 | Mar 18, 2014 | — |
Addendum 1: Struct, arch, t24, final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 18, 2014 | Mar 18, 2014 | — |
Building plan review Building Inspection · BLDG | Mar 18, 2014 | Apr 18, 2014 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 19, 2014 | Apr 4, 2014 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 4, 2014 | Apr 30, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Apr 18, 2014 | May 6, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 23, 2014 | Apr 25, 2014 | — |
Permit Processing Center Building Inspection · PPC | May 7, 2014 | May 7, 2014 | — |
Central Permit Bureau Building Inspection · CPB | May 7, 2014 | May 12, 2014 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $514,034
| Name | Role | License on permit |
|---|---|---|
| Lorin Frederick Hill Lorin Hill, Architect | Architect | C23266 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2020