250 Roosevelt Wy #0
San Francisco permit 201309045934 · Castro/Upper Market
New 735 sq ft top floor master suite addition to top unit of (e) 3 unit bldg. existing two stories proposed three stories.
- Filed
- Sep 4, 2013
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 13 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 4, 2013 | Sep 4, 2013 | — |
Central Permit Bureau Building Inspection · CPB | Sep 4, 2013 | Sep 4, 2013 | — |
Zoning review Planning · CP-ZOC | Sep 4, 2013 | Apr 9, 2017 | — |
Planning neighborhood notice Planning · CP-NP | May 6, 2014 | May 29, 2014 | — |
Planning discretionary review Planning · CP-DR | Jun 12, 2014 | In progress | — |
Building plan review Building Inspection · BLDG | Apr 10, 2017 | May 5, 2017 | — |
Building plan review Building Inspection · BLDG | May 26, 2017 | May 26, 2017 | — |
Building plan review Building Inspection · BLDG | Apr 18, 2019 | In progress | — |
Permit Processing Center Building Inspection · PPC | Nov 15, 2022 | Nov 15, 2022 | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Hildegard Anna Richardson | Architect | C011183 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022