1 Henry Adams St
San Francisco permit 201309247590 · Mission Bay
To demolish 1 story retail / whole sale building. ** maher: compliance with ordinance no# 155-13 not required **
- Filed
- Sep 24, 2013
- Issued
- Sep 5, 2014 (11 months after filing)
- Completed
- Aug 11, 2015 (11 months after issuance)
- Review stops
- 8 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 25, 2013 | Sep 25, 2013 | — |
Zoning review Planning · CP-ZOC | Sep 27, 2013 | Oct 28, 2013 | — |
Building plan review Building Inspection · BLDG | Oct 29, 2013 | Nov 15, 2013 | — |
Street use and mapping Public Works · DPW-BSM | Nov 19, 2013 | Nov 21, 2013 | — |
Public health review Public Health · HEALTH | Nov 21, 2013 | Jan 8, 2014 | — |
Zoning review Planning · CP-ZOC | Mar 6, 2014 | Mar 28, 2014 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2014 | Mar 31, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Mar 31, 2014 | Sep 5, 2014 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Demolitions
- Status
- Complete
- Estimated cost
- $3,700
| Name | Role | License on permit |
|---|---|---|
| Richard Doyle Beard Bar | Architect | C12947 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026