1512 20th St
San Francisco permit 201310290519 · Potrero Hill
Remove (e) roof. increase height of (e) 2 story bldg & add (n) mezz. add (n0) roof deck @ single story addition) 2 story plus single story addition@ rear. remodel interior of(e)mbldg. rehabilitate front facade with (n) windows in (e) opening. replace (e) garage door with(n) gates. all mep work to
- Filed
- Oct 29, 2013
- Issued
- Nov 12, 2015 (24 months after filing)
- Completed
- Not completed yet
- Review stops
- 29 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 29, 2013 | Oct 29, 2013 | — |
Zoning review Planning · CP-ZOC | Oct 29, 2013 | Apr 9, 2015 | — |
Planning neighborhood notice Planning · CP-NP | Oct 29, 2014 | Dec 31, 2014 | — |
Zoning review Planning · CP-ZOC | Dec 31, 2014 | Apr 2, 2015 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2015 | Jun 1, 2015 | — |
Building plan review Building Inspection · BLDG | Jun 1, 2015 | Sep 22, 2015 | — |
Fire prevention review Fire Department · SFFD | Jun 2, 2015 | Jul 10, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2015 | Jun 5, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 23, 2015 | Oct 2, 2015 | — |
Zoning review Planning · CP-ZOC | Oct 2, 2015 | Oct 9, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Oct 13, 2015 | Oct 28, 2015 | — |
Permit Processing Center Building Inspection · PPC | Oct 28, 2015 | Oct 28, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Oct 28, 2015 | Nov 12, 2015 | — |
Addendum 1: Struct,arch,foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 16, 2015 | Nov 16, 2015 | — |
Building plan review Building Inspection · BLDG | Nov 16, 2015 | Dec 8, 2015 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 16, 2015 | Apr 12, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 29, 2016 | Mar 30, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2016 | Mar 21, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Mar 21, 2016 | Apr 8, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2016 | Apr 13, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2016 | Apr 14, 2016 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2016 | Apr 20, 2016 | — |
Permit Processing Center Building Inspection · PPC | Apr 20, 2016 | Apr 20, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Apr 20, 2016 | Jun 9, 2016 | — |
Addendum 2: Mechanical,electrical,plumbing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 7, 2016 | Mar 7, 2016 | — |
Building plan review Building Inspection · BLDG | Mar 7, 2016 | Mar 7, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 7, 2016 | Apr 13, 2016 | — |
Permit Processing Center Building Inspection · PPC | Apr 12, 2016 | Apr 13, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2016 | Jun 9, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Cary S Bernstein Cary Bernstein Architecture | Architect | C27690 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026