312 Green St
San Francisco permit 201311131794 · North Beach
Ground & 2nd floor remodel & 3rd & 4th story addition.
- Filed
- Nov 13, 2013
- Issued
- Oct 26, 2015 (23 months after filing)
- Completed
- Mar 19, 2024 (101 months after issuance)
- Review stops
- 28 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 13, 2013 | Nov 13, 2013 | — |
Zoning review Planning · CP-ZOC | Nov 13, 2013 | Mar 9, 2015 | — |
Planning neighborhood notice Planning · CP-NP | Jun 2, 2014 | Mar 9, 2015 | — |
Planning discretionary review Planning · CP-DR | Jul 21, 2014 | Mar 9, 2015 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2015 | Mar 30, 2015 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2015 | Aug 19, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2015 | Apr 8, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2015 | Apr 14, 2015 | — |
Fire prevention review Fire Department · SFFD | Aug 19, 2015 | Sep 23, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2015 | Sep 29, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2015 | Oct 6, 2015 | — |
Zoning review Planning · CP-ZOC | Oct 6, 2015 | Oct 16, 2015 | — |
Permit Processing Center Building Inspection · PPC | Oct 16, 2015 | Oct 19, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Oct 19, 2015 | Oct 26, 2015 | — |
Addendum 1: Struc, arch, mech, t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 26, 2016 | Feb 26, 2016 | — |
Building plan review Building Inspection · BLDG | Feb 26, 2016 | Oct 6, 2016 | — |
Structural plan approval Building Inspection · PAD-STR | Feb 29, 2016 | Sep 14, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 25, 2016 | Sep 15, 2016 | — |
Fire prevention review Fire Department · SFFD | Aug 11, 2016 | Sep 7, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2016 | Nov 18, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 6, 2016 | Oct 14, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2016 | Nov 22, 2016 | — |
Permit Processing Center Building Inspection · PPC | Nov 22, 2016 | Dec 7, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Dec 7, 2016 | Aug 2, 2017 | — |
Addendum 2: As built condition
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 18, 2018 | Sep 18, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 18, 2018 | Sep 19, 2018 | — |
Permit Processing Center Building Inspection · PPC | Sep 19, 2018 | Sep 19, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2018 | Oct 19, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $476,000
| Name | Role | License on permit |
|---|---|---|
| Bruno P Kanter | Architect | C26422 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025