660 Indiana St
San Francisco permit 201312244989 · Potrero Hill
Erect 5 stories, 60 dwelling units.
- Filed
- Dec 24, 2013
- Issued
- Dec 24, 2014 (12 months after filing)
- Completed
- May 20, 2019 (53 months after issuance)
- Review stops
- 39 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 10 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 27, 2013 | Dec 27, 2013 | — |
Zoning review Planning · CP-ZOC | Dec 27, 2013 | Jul 31, 2014 | — |
Building plan review Building Inspection · BLDG | Jul 31, 2014 | Aug 15, 2014 | — |
Building plan review Building Inspection · BLDG | Aug 15, 2014 | Nov 14, 2014 | — |
Fire prevention review Fire Department · SFFD | Oct 1, 2014 | Nov 10, 2014 | — |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2014 | Dec 18, 2014 | — |
Public health review Public Health · HEALTH | Nov 17, 2014 | Nov 17, 2014 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 18, 2014 | Dec 2, 2014 | — |
Development fee collection Building Inspection · DFCU | Nov 20, 2014 | Nov 20, 2014 | — |
Building plan review Building Inspection · BLDG | Dec 17, 2014 | Dec 17, 2014 | — |
Permit Processing Center Building Inspection · PPC | Dec 22, 2014 | Dec 22, 2014 | — |
Central Permit Bureau Building Inspection · CPB | Dec 22, 2014 | Dec 24, 2014 | — |
Addendum 1: Superstructure.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 12, 2015 | Mar 12, 2015 | — |
Building plan review Building Inspection · BLDG | Mar 12, 2015 | Apr 22, 2015 | — |
Permit Processing Center Building Inspection · PPC | Apr 22, 2015 | Apr 22, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Apr 22, 2015 | Jun 2, 2015 | — |
Addendum 2: Architectural / mep / landscaping.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Public Utilities Commission review Public Utilities · SFPUC | Jan 7, 2015 | Jan 8, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2015 | Apr 15, 2015 | — |
Building plan review Building Inspection · BLDG | Apr 16, 2015 | Jan 7, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2015 | Oct 1, 2015 | — |
Fire prevention review Fire Department · SFFD | Jun 18, 2015 | Dec 21, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2016 | Jan 21, 2016 | — |
Fire prevention review Fire Department · SFFD | Feb 9, 2016 | Feb 9, 2016 | — |
Fire prevention review Fire Department · SFFD | Feb 9, 2016 | Feb 9, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 16, 2016 | Mar 4, 2016 | — |
Permit Processing Center Building Inspection · PPC | Mar 10, 2016 | Mar 10, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 10, 2016 | Mar 14, 2016 | — |
Addendum 3: Fire protection.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 29, 2015 | Oct 29, 2015 | — |
Fire prevention review Fire Department · SFFD | Oct 29, 2015 | Jun 7, 2016 | — |
Permit Processing Center Building Inspection · PPC | Jun 7, 2016 | Jun 7, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Jun 7, 2016 | Jun 9, 2016 | — |
Addendum 4: Fire alarm.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 24, 2016 | May 24, 2016 | — |
Fire prevention review Fire Department · SFFD | May 24, 2016 | Feb 21, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 23, 2017 | Feb 23, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2017 | Feb 24, 2017 | — |
Addendum 5: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 2, 2016 | Aug 2, 2016 | — |
Fire prevention review Fire Department · SFFD | Aug 2, 2016 | Feb 9, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 10, 2017 | Feb 10, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 10, 2017 | Feb 24, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $10,000,000
| Name | Role | License on permit |
|---|---|---|
| Owen Cheatham Kennerly Kennerly Architecture | Architect | C29565 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026