2505 Broadway
San Francisco permit 201401065671 · Pacific Heights
This project consists of a new garage in the basement, a new elevator & remodel of the first & second floors. no change to height or use. no change to front door/entry.
- Filed
- Jan 6, 2014
- Issued
- Sep 29, 2017 (45 months after filing)
- Completed
- Sep 3, 2019 (23 months after issuance)
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 6, 2014 | Jan 6, 2014 | — |
Zoning review Planning · CP-ZOC | Jan 6, 2014 | Sep 26, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Aug 2, 2016 | Sep 26, 2016 | — |
Building plan review Building Inspection · BLDG | Sep 27, 2016 | Jan 12, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 12, 2017 | Jan 17, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 17, 2017 | Feb 2, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 2, 2017 | Feb 2, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2017 | Sep 29, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | May 24, 2017 | May 24, 2017 | — |
Addendum 1: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 16, 2018 | Jan 16, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 16, 2018 | Apr 25, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2018 | Apr 30, 2018 | — |
Building plan review Building Inspection · BLDG | May 1, 2018 | May 1, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 1, 2018 | May 1, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 1, 2018 | May 2, 2018 | — |
Addendum 2: Architectural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2018 | May 3, 2018 | — |
Building plan review Building Inspection · BLDG | May 3, 2018 | May 15, 2018 | — |
Building plan review Building Inspection · BLDG | May 25, 2018 | May 25, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2018 | May 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | May 30, 2018 | Jun 22, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 13, 2018 | Jun 14, 2018 | — |
Zoning review Planning · CP-ZOC | Jun 25, 2018 | Jul 27, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jul 30, 2018 | Jul 30, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2018 | Aug 2, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $320,000
| Name | Role | License on permit |
|---|---|---|
| Babac Doane Babac Doane Architect | Architect | C22401 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022