CheckMyDesigner

238 Presidio Av

San Francisco permit 201404244103 · Presidio Heights

AdditionFull plan reviewComplete
Street view · May 2019
Google Street View of 238 Presidio Av, May 2019
Scope of work
As written on the permit application.

Remodel existing single family residence. reconfigure interior walls at all levels. add 4th floor, 1 & 2 story rear yard addition. no work to front facade. ** maher: compliance with ordinance no# 155-13 not required **

Timeline
Key dates from the city record.
Filed
Apr 24, 2014
Issued
Apr 21, 2015 (12 months after filing)
Completed
Mar 29, 2017 (23 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
23 stops across 4 departments
Comments issued
Not recorded for this permit
Put on hold
5 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 24, 2014—

Zoning review

Planning · CP-ZOC

Jan 26, 2015—

Planning neighborhood notice

Planning · CP-NP

Jan 26, 2015—

Planning discretionary review

Planning · CP-DR

Oct 22, 2014—

Building plan review

Building Inspection · BLDG

Mar 13, 2015—

Street use and mapping

Public Works · DPW-BSM

Mar 25, 2015—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 19, 2015—

Zoning review

Planning · CP-ZOC

Apr 16, 2015—

Permit Processing Center

Building Inspection · PPC

Apr 17, 2015—

Central Permit Bureau

Building Inspection · CPB

Apr 21, 2015—

Addendum 1: Arch / structural / t-24 / final.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 21, 2015—

Building plan review

Building Inspection · BLDG

Sep 23, 2015—

Structural plan approval

Building Inspection · PAD-STR

May 28, 2015—

Mechanical and energy plan review

Building Inspection · MECH

Nov 17, 2015—

Street use and mapping

Public Works · DPW-BSM

Nov 5, 2015—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 6, 2015—

Zoning review

Planning · CP-ZOC

Nov 19, 2015—

Building plan review

Building Inspection · BLDG

Jan 6, 2016—

Structural plan approval

Building Inspection · PAD-STR

Dec 11, 2015—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 7, 2016—

Street use and mapping

Public Works · DPW-BSM

Jan 15, 2016—

Permit Processing Center

Building Inspection · PPC

Jan 19, 2016—

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2016—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$800,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
John F Dorr

Doma Architects

ArchitectC-28936
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201404244103 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record