Horizontal/vertical addition add 4th floor addition w/ roof deck, excavation at rear garage level, full seismic upgrace and sprinkler system.

Timeline
Key dates from the city record.
Filed
Aug 19, 2014
Issued
Jul 10, 2017 (35 months after filing)
Completed
May 23, 2019 (22 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
6 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 9, 2014—

Zoning review

Planning · CP-ZOC

Feb 23, 2017—

Planning neighborhood notice

Planning · CP-NP

Feb 3, 2017—

Building plan review

Building Inspection · BLDG

Jun 22, 2017—

Fire prevention review

Fire Department · SFFD

Jun 30, 2017—

Street use and mapping

Public Works · DPW-BSM

Jun 2, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 16, 2017—

Permit Processing Center

Building Inspection · PPC

Jul 3, 2017—

Central Permit Bureau

Building Inspection · CPB

Jul 10, 2017—

Addendum 1: Arch / structural / t-24 / final.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 1, 2017—

Building plan review

Building Inspection · BLDG

Aug 14, 2017—

Structural plan approval

Building Inspection · PAD-STR

Aug 14, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2017—

Fire prevention review

Fire Department · SFFD

Sep 12, 2017—

Street use and mapping

Public Works · DPW-BSM

Sep 21, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 14, 2017—

Permit Processing Center

Building Inspection · PPC

Sep 22, 2017—

Central Permit Bureau

Building Inspection · CPB

Sep 27, 2017—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Edward Davis Morris

Kerman Morris Architects

ArchitectC-24585
Jackie Mckay DetamoreArchitectC30931
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201408194152 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record