1560 Dolores St
San Francisco permit 201410159002 · Noe Valley
Horizontal & vertical addition to existing single family home, one addition unit @ third and four floor.
- Filed
- Oct 15, 2014
- Issued
- Mar 8, 2016 (17 months after filing)
- Completed
- Oct 26, 2018 (32 months after issuance)
- Review stops
- 21 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 15, 2014 | Oct 15, 2014 | — |
Zoning review Planning · CP-ZOC | Oct 16, 2014 | Dec 28, 2015 | — |
Planning neighborhood notice Planning · CP-NP | Oct 23, 2015 | Dec 28, 2015 | — |
Building plan review Building Inspection · BLDG | Dec 29, 2015 | Jan 22, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 22, 2016 | Feb 3, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2016 | Feb 9, 2016 | — |
Fire prevention review Fire Department · SFFD | Feb 12, 2016 | Mar 3, 2016 | — |
Permit Processing Center Building Inspection · PPC | Mar 3, 2016 | Mar 3, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2016 | Mar 8, 2016 | — |
Addendum 1: Arch, mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 25, 2016 | Jul 25, 2016 | — |
Building plan review Building Inspection · BLDG | Jul 25, 2016 | Oct 3, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2016 | Sep 19, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2016 | Sep 7, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2016 | Sep 21, 2016 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2016 | Oct 4, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2016 | Oct 6, 2016 | — |
Addendum 2: Foundation & superstricture
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 4, 2016 | Nov 4, 2016 | — |
Building plan review Building Inspection · BLDG | Nov 4, 2016 | Nov 15, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2016 | Nov 18, 2016 | — |
Permit Processing Center Building Inspection · PPC | Nov 21, 2016 | Nov 21, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Nov 21, 2016 | Dec 13, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $780,000
| Name | Role | License on permit |
|---|---|---|
| Siavash Tahbazof | Engineer | C38827 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024