CheckMyDesigner

2283 Shafter Av

San Francisco permit 201410219510 · Bayview Hunters Point

New buildingFull plan reviewIssued
Street view · Sep 2026
Google Street View of 2283 Shafter Av, Sep 2026
Scope of work
As written on the permit application.

Erect 1-story, type 3, commercial kitchen food preparation building.

Timeline
Key dates from the city record.
Filed
Oct 21, 2014
Issued
Aug 10, 2016 (22 months after filing)
Completed
Not completed yet
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
6 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 7, 2014—

Zoning review

Planning · CP-ZOC

Aug 14, 2015—

Building plan review

Building Inspection · BLDG

Sep 4, 2015—

Fire prevention review

Fire Department · SFFD

Sep 16, 2015—

Street use and mapping

Public Works · DPW-BSM

Sep 22, 2015—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 19, 2015—

Public health review

Public Health · HEALTH

Oct 28, 2015—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 29, 2015—

Street use and mapping

Public Works · DPW-BSM

Nov 9, 2015—

Zoning review

Planning · CP-ZOC

Nov 12, 2015—

Permit Processing Center

Building Inspection · PPC

Nov 12, 2015—

Central Permit Bureau

Building Inspection · CPB

Aug 10, 2016—

Addendum 1: Grading / foundation.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 7, 2016—

Building plan review

Building Inspection · BLDG

Apr 4, 2017—

Street use and mapping

Public Works · DPW-BSM

Aug 14, 2019—

Permit Processing Center

Building Inspection · PPC

Aug 15, 2019—

Central Permit Bureau

Building Inspection · CPB

In progress—

Addendum 2: Arch/superstruc/mech/ ele/ t-24.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 29, 2017—

Building plan review

Building Inspection · BLDG

Mar 27, 2018—

Mechanical and energy plan review

Building Inspection · MECH

Nov 28, 2017—

Street use and mapping

Public Works · DPW-BSM

Sep 19, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 1, 2017—

Electrical plan review

Building Inspection · MECH-E

Mar 21, 2018—

Zoning review

Planning · CP-ZOC

Sep 26, 2019—

Mechanical and energy plan review

Building Inspection · MECH

Sep 27, 2019—

Permit Processing Center

Building Inspection · PPC

Oct 16, 2019—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Issued
Estimated cost
$700,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Tommy Kam-Tai Kwan

Tommy Kwan Associates

ArchitectC13926
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201410219510 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record