2283 Shafter Av
San Francisco permit 201410219510 · Bayview Hunters Point
Erect 1-story, type 3, commercial kitchen food preparation building.
- Filed
- Oct 21, 2014
- Issued
- Aug 10, 2016 (22 months after filing)
- Completed
- Not completed yet
- Review stops
- 27 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 7, 2014 | Nov 7, 2014 | — |
Zoning review Planning · CP-ZOC | Dec 30, 2014 | Aug 14, 2015 | — |
Building plan review Building Inspection · BLDG | Aug 19, 2015 | Sep 4, 2015 | — |
Fire prevention review Fire Department · SFFD | Sep 4, 2015 | Sep 16, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2015 | Sep 22, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 22, 2015 | Oct 19, 2015 | — |
Public health review Public Health · HEALTH | Oct 20, 2015 | Oct 28, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2015 | Oct 29, 2015 | — |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2015 | Nov 9, 2015 | — |
Zoning review Planning · CP-ZOC | Nov 9, 2015 | Nov 12, 2015 | — |
Permit Processing Center Building Inspection · PPC | Nov 12, 2015 | Nov 12, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Nov 12, 2015 | Aug 10, 2016 | — |
Addendum 1: Grading / foundation.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 7, 2016 | Nov 7, 2016 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2016 | Apr 4, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2016 | Aug 14, 2019 | — |
Permit Processing Center Building Inspection · PPC | Aug 15, 2019 | Aug 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2019 | In progress | — |
Addendum 2: Arch/superstruc/mech/ ele/ t-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 29, 2017 | Mar 29, 2017 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2017 | Mar 27, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 27, 2017 | Nov 28, 2017 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2017 | Sep 19, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2017 | Jun 1, 2017 | — |
Electrical plan review Building Inspection · MECH-E | Nov 28, 2017 | Mar 21, 2018 | — |
Zoning review Planning · CP-ZOC | Sep 20, 2019 | Sep 26, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2019 | Sep 27, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 16, 2019 | Oct 16, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2019 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $700,000
| Name | Role | License on permit |
|---|---|---|
| Tommy Kam-Tai Kwan Tommy Kwan Associates | Architect | C13926 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026