14 Laidley St
San Francisco permit 201411121252 · Glen Park
Rear, front, side addition w/ two stories over basement, vertical addition to add 1 story, add new garage interior renovation of existin 2 units building, elec, mech, plumb under sep permits.
- Filed
- Nov 12, 2014
- Issued
- Oct 18, 2016 (23 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 12, 2014 | Nov 12, 2014 | — |
Zoning review Planning · CP-ZOC | Nov 12, 2014 | Aug 8, 2016 | — |
Building plan review Building Inspection · BLDG | Aug 9, 2016 | Sep 8, 2016 | — |
Fire prevention review Fire Department · SFFD | Sep 8, 2016 | Sep 9, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Sep 9, 2016 | Sep 19, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2016 | Oct 6, 2016 | — |
Development fee collection Building Inspection · DFCU | Oct 4, 2016 | Oct 4, 2016 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2016 | Oct 6, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2016 | Oct 18, 2016 | — |
Addendum 1: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 1, 2017 | Dec 1, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 4, 2017 | Jan 12, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 4, 2017 | Mar 15, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Feb 6, 2018 | Mar 16, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 19, 2018 | Mar 21, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2018 | In progress | — |
Addendum 2: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 26, 2018 | Mar 26, 2018 | — |
Building plan review Building Inspection · BLDG | Mar 26, 2018 | Apr 12, 2018 | — |
Building plan review Building Inspection · BLDG | Mar 26, 2018 | May 23, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | May 7, 2018 | May 31, 2018 | — |
Fire prevention review Fire Department · SFFD | May 31, 2018 | Jun 26, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 15, 2018 | Jul 10, 2018 | — |
Fire prevention review Fire Department · SFFD | Jul 11, 2018 | Jul 13, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jul 11, 2018 | Jul 13, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jul 13, 2018 | Aug 3, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Cary S Bernstein | Architect | C27690 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026