845 Holloway Av #0
San Francisco permit 201412103468 · Oceanview/Merced/Ingleside
Addition of 1 unit on an (e) 2-story mixed used project which already has 3 apartment units over retail.
- Filed
- Dec 10, 2014
- Issued
- Oct 20, 2016 (22 months after filing)
- Completed
- Jun 5, 2023 (79 months after issuance)
- Review stops
- 27 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Zoning review Planning · CP-ZOC | Feb 25, 2015 | Oct 26, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2015 | Mar 4, 2015 | — |
Planning neighborhood notice Planning · CP-NP | Aug 14, 2015 | Oct 26, 2015 | — |
Building plan review Building Inspection · BLDG | Oct 27, 2015 | Nov 18, 2015 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2015 | Jan 14, 2016 | — |
Fire prevention review Fire Department · SFFD | Nov 18, 2015 | Nov 24, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 24, 2015 | Dec 2, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 2, 2015 | Dec 2, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 14, 2016 | Apr 6, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Apr 6, 2016 | Apr 11, 2016 | — |
Fire prevention review Fire Department · SFFD | Jun 17, 2016 | Jun 17, 2016 | — |
Zoning review Planning · CP-ZOC | Jun 17, 2016 | Aug 18, 2016 | — |
Building plan review Building Inspection · BLDG | Aug 19, 2016 | Aug 19, 2016 | — |
Fire prevention review Fire Department · SFFD | Aug 19, 2016 | Aug 22, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2016 | Aug 31, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2016 | Sep 6, 2016 | — |
Development fee collection Building Inspection · DFCU | Sep 7, 2016 | Sep 7, 2016 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2016 | Sep 7, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Sep 7, 2016 | Oct 20, 2016 | — |
Addendum 1: Arch,struct,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 26, 2017 | Jan 26, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 27, 2017 | Sep 25, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2017 | Sep 25, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 21, 2017 | Oct 31, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jun 6, 2017 | May 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2017 | Jun 23, 2017 | — |
Permit Processing Center Building Inspection · PPC | Sep 25, 2019 | Sep 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2019 | Jan 24, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $170,000
| Name | Role | License on permit |
|---|---|---|
| Hafsa Burt Hb+A Architects | Architect | C30584 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2019