401 Potrero Av
San Francisco permit 201505015169 · Mission
Remodel (e) snack shop and 2 bay structure into 1,483 sf convenience store. remodel (e) fuel canopy to include (n) 572 sf. canopy extension covering (2) fuel dispenser and canopy column. maher ordinance 155-13 not required
- Filed
- May 1, 2015
- Issued
- Jul 6, 2017 (26 months after filing)
- Completed
- Not completed yet
- Review stops
- 34 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 1, 2015 | May 1, 2015 | — |
Zoning review Planning · CP-ZOC | May 1, 2015 | Apr 8, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Dec 30, 2015 | Apr 8, 2016 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2016 | Jun 7, 2017 | — |
Fire prevention review Fire Department · SFFD | May 5, 2016 | Apr 26, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2016 | Jun 29, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2017 | May 12, 2017 | — |
Zoning review Planning · CP-ZOC | Jun 7, 2017 | Jun 13, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 14, 2017 | Jun 14, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jun 15, 2017 | Jun 29, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jun 29, 2017 | Jul 6, 2017 | — |
Addendum 1: Arch / structural / t-24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 8, 2018 | Aug 8, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 10, 2018 | Sep 11, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2018 | Sep 12, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2018 | Sep 11, 2018 | — |
Electrical plan review Building Inspection · MECH-E | Sep 11, 2018 | Sep 11, 2018 | — |
Fire prevention review Fire Department · SFFD | Sep 12, 2018 | Nov 29, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Nov 29, 2018 | Jan 29, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2018 | Dec 6, 2018 | — |
Public health review Public Health · HEALTH | Dec 7, 2018 | Dec 27, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2019 | Jan 31, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2019 | Feb 26, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2019 | Feb 1, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Feb 1, 2019 | Feb 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2020 | Feb 28, 2020 | — |
Addendum 2: Architectural for canopy
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 8, 2018 | Aug 8, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 10, 2018 | Sep 11, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2018 | Sep 13, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 13, 2018 | Oct 2, 2018 | — |
Electrical plan review Building Inspection · MECH-E | Oct 2, 2018 | Nov 29, 2018 | — |
Fire prevention review Fire Department · SFFD | Oct 29, 2018 | Oct 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2018 | Jan 29, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 30, 2019 | Jan 30, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jan 30, 2019 | Feb 24, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Muthana Ismail Ibrahim M I Architects, Inc. | Architect | C29627 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2016