325 Holloway Av
San Francisco permit 201506239695 · Oceanview/Merced/Ingleside
Horizontal addition. removal of (e) roof deck & exterior stair. construction of new bedroom & bathroom addition on 2nd floor & new exterior stair. remodeling of (e) laundry & bathroom at 2nd floor. install new skylights.
- Filed
- Jun 23, 2015
- Issued
- Feb 12, 2016 (8 months after filing)
- Completed
- Sep 28, 2016 (8 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 26, 2015 | Jun 26, 2015 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2015 | Nov 19, 2015 | — |
Planning neighborhood notice Planning · CP-NP | Sep 21, 2015 | Nov 19, 2015 | — |
Building plan review Building Inspection · BLDG | Nov 20, 2015 | Dec 1, 2015 | — |
Building plan review Building Inspection · BLDG | Dec 29, 2015 | Dec 29, 2015 | — |
Building plan review Building Inspection · BLDG | Dec 29, 2015 | Jan 8, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2016 | Jan 28, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2016 | Jan 27, 2016 | — |
Permit Processing Center Building Inspection · PPC | Jan 28, 2016 | Jan 28, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2016 | Feb 12, 2016 | — |
Addendum 1: Arch/struct/title 24/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 16, 2016 | Feb 16, 2016 | — |
Building plan review Building Inspection · BLDG | Feb 16, 2016 | Feb 24, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2016 | Feb 24, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2016 | Feb 29, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 2, 2016 | Mar 8, 2016 | — |
Zoning review Planning · CP-ZOC | Mar 8, 2016 | Mar 11, 2016 | — |
Permit Processing Center Building Inspection · PPC | Mar 14, 2016 | Mar 14, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 14, 2016 | Mar 25, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Robert Allen Boles Beausoleil Architecture | Architect | C016978 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025