63 Carmel St
San Francisco permit 201507010460 · Inner Sunset
Vertical & lateral addition to (e) sfh. no change of use. occupancy or building type. additional rooms to be added 1 bath, 1 office & 1 family room.
- Filed
- Jul 1, 2015
- Issued
- Nov 16, 2017 (29 months after filing)
- Completed
- Feb 13, 2025 (87 months after issuance)
- Review stops
- 22 stops across 4 departments
- Comments issued
- None
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 7, 2015 | Oct 7, 2015 | — |
Zoning review Planning · CP-ZOC | Oct 7, 2015 | Jul 13, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Mar 27, 2017 | Jul 13, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 14, 2017 | Aug 29, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2017 | Sep 1, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2017 | Sep 27, 2017 | — |
Zoning review Planning · CP-ZOC | Sep 27, 2017 | Oct 26, 2017 | — |
Development fee collection Building Inspection · DFCU | Oct 27, 2017 | Oct 27, 2017 | — |
Permit Processing Center Building Inspection · PPC | Oct 27, 2017 | Oct 30, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 30, 2017 | Nov 16, 2017 | — |
Addendum 1: Arch,struc,mech,elec
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 19, 2018 | Jun 19, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 19, 2018 | Jun 26, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2018 | Jul 8, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Aug 29, 2018 | Jul 22, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2018 | Sep 8, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 14, 2018 | Dec 14, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 26, 2019 | Jun 26, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 24, 2019 | Jul 25, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jul 24, 2019 | Jul 30, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 25, 2019 | Jul 29, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2019 | Aug 2, 2019 | — |
Addendum 2: Withdrawn
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2024 | May 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $650,000
| Name | Role | License on permit |
|---|---|---|
| Luke Caspar Ogrydziak Ogrydziak Prillinger Arch | Architect | C29338 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025