2501 California St
San Francisco permit 201508043239 · Pacific Heights
Convenience store. erect 1 story, type 5-b convenience store for shell gas station. gas station sits in 3 lots, will be merge into 1 lot. will use 2501 california st for the address.
- Filed
- Aug 4, 2015
- Issued
- Mar 14, 2016 (7 months after filing)
- Completed
- Jul 18, 2017 (16 months after issuance)
- Review stops
- 25 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 4, 2015 | Aug 4, 2015 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2015 | Jan 7, 2016 | — |
Building plan review Building Inspection · BLDG | Jan 7, 2016 | Jan 25, 2016 | — |
Fire prevention review Fire Department · SFFD | Jan 15, 2016 | Jan 21, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jan 25, 2016 | Jan 28, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 28, 2016 | Feb 9, 2016 | — |
Public health review Public Health · HEALTH | Feb 9, 2016 | Feb 12, 2016 | — |
Fire prevention review Fire Department · SFFD | Feb 18, 2016 | Feb 25, 2016 | — |
Zoning review Planning · CP-ZOC | Mar 7, 2016 | Mar 7, 2016 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2016 | Mar 7, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2016 | Mar 14, 2016 | — |
Addendum 1: Struct,arch,t24,mep, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 4, 2016 | May 4, 2016 | — |
Building plan review Building Inspection · BLDG | May 4, 2016 | Oct 6, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | May 17, 2016 | Jun 7, 2016 | — |
Fire prevention review Fire Department · SFFD | Jun 10, 2016 | Jun 15, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jun 15, 2016 | Aug 12, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2016 | Jun 23, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2016 | Jun 24, 2016 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 27, 2016 | Aug 3, 2016 | — |
Zoning review Planning · CP-ZOC | Aug 12, 2016 | Aug 19, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 26, 2016 | Aug 26, 2016 | — |
Permit Processing Center Building Inspection · PPC | Aug 26, 2016 | Oct 21, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2016 | Oct 7, 2016 | — |
Zoning review Planning · CP-ZOC | Oct 7, 2016 | Oct 21, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2016 | Nov 9, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $900,000
| Name | Role | License on permit |
|---|---|---|
| Muthana Ismail Ibrahim M I Architects, Inc. | Architect | C29627 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024