89 Alpine Tr
San Francisco permit 201508073661 · Haight Ashbury
Demo (e) walls, windows & doors. remove (e) fixtures & finishes. construction of new walls, doors, window & roof deck. exterior work includes new finishes, doors, windows & partial lightwell infill. construction will include fully auto. sprinkler system.
- Filed
- Aug 7, 2015
- Issued
- Apr 19, 2016 (8 months after filing)
- Completed
- Jan 26, 2018 (21 months after issuance)
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 7, 2015 | Aug 7, 2015 | — |
Apartment and hotel inspection Building Inspection · HIS | Aug 14, 2015 | Aug 14, 2015 | — |
Zoning review Planning · CP-ZOC | Sep 3, 2015 | Sep 3, 2015 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2015 | Sep 8, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2015 | Sep 15, 2015 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2015 | Dec 22, 2015 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 2, 2015 | Nov 23, 2015 | — |
Fire prevention review Fire Department · SFFD | Nov 12, 2015 | Nov 17, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2015 | Dec 29, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2016 | Jan 5, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2016 | Jan 8, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jan 11, 2016 | Feb 4, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 9, 2016 | Feb 16, 2016 | — |
Permit Processing Center Building Inspection · PPC | Feb 16, 2016 | Feb 16, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Feb 16, 2016 | Apr 19, 2016 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $593,500
| Name | Role | License on permit |
|---|---|---|
| Brian T Milford Martinkovie Milford Arch | Architect | C33430 |
| Babak Vaziri Vaziri Structural Engineering | Engineer | S3985 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025