1394 Harrison St
San Francisco permit 201508194769 · South of Market
To erect 6 stories, no basement, type i-b, 67 residential units with commercial building. (r-2,m,u,s-2) ** ssordinance-extended required **
- Filed
- Aug 19, 2015
- Issued
- Jul 20, 2018 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 32 stops across 6 departments
- Comments issued
- None
- Put on hold
- 11 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 21, 2015 | Aug 21, 2015 | — |
Zoning review Planning · CP-ZOC | Aug 21, 2015 | Oct 5, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Jun 1, 2016 | Oct 5, 2016 | — |
Planning discretionary review Planning · CP-DR | Jul 19, 2016 | Oct 5, 2016 | — |
Building plan review Building Inspection · BLDG | Oct 7, 2016 | Apr 11, 2018 | — |
Fire prevention review Fire Department · SFFD | Nov 15, 2016 | Apr 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 28, 2016 | Jan 4, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2018 | Mar 21, 2018 | — |
Public health review Public Health · HEALTH | Apr 30, 2018 | May 3, 2018 | — |
Zoning review Planning · CP-ZOC | May 3, 2018 | May 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | May 30, 2018 | May 31, 2018 | — |
Development fee collection Building Inspection · DFCU | May 31, 2018 | Jun 5, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 31, 2018 | Jun 5, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 5, 2018 | Jul 20, 2018 | — |
Addendum 1: Foundation,superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 4, 2019 | Jun 4, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 4, 2019 | Oct 11, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Oct 11, 2019 | Jan 8, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 9, 2020 | Jan 9, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2020 | Jan 27, 2020 | — |
Addendum 2: Arch,mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 20, 2020 | Feb 20, 2020 | — |
Building plan review Building Inspection · BLDG | Feb 21, 2020 | Jan 13, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 27, 2020 | Jan 18, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 27, 2020 | In progress | — |
Fire prevention review Fire Department · SFFD | Mar 19, 2021 | Apr 8, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 20, 2021 | May 18, 2021 | — |
Public health review Public Health · HEALTH | Apr 29, 2021 | May 5, 2021 | — |
Fire prevention review Fire Department · SFFD | May 26, 2023 | May 26, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Cancelled
- Estimated cost
- $8,320,974
| Name | Role | License on permit |
|---|---|---|
| Mark David Macy Macy Architecture | Architect | C20541 |
| Jonathan Ennis Bde Architecture | Architect | C27221 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026