CheckMyDesigner

2779 Mission St

San Francisco permit 201508315701 · Mission

AdditionFull plan reviewComplete
Street view · Sep 2026
Google Street View of 2779 Mission St, Sep 2026
Scope of work
As written on the permit application.

One story horizontal addition for dry storage and refrigerator at the rear of (e) restaurant.

Timeline
Key dates from the city record.
Filed
Aug 31, 2015
Issued
Aug 15, 2016 (11 months after filing)
Completed
Nov 18, 2020 (51 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
Once

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 1, 2015—

Zoning review

Planning · CP-ZOC

Mar 1, 2016—

Planning neighborhood notice

Planning · CP-NP

Mar 1, 2016—

Building plan review

Building Inspection · BLDG

Jun 24, 2016—

Fire prevention review

Fire Department · SFFD

Mar 23, 2016—

Street use and mapping

Public Works · DPW-BSM

Jun 30, 2016—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 12, 2016—

Public health review

Public Health · HEALTH

Jul 14, 2016—

Fire prevention review

Fire Department · SFFD

Jul 19, 2016—

Zoning review

Planning · CP-ZOC

Jul 22, 2016—

Permit Processing Center

Building Inspection · PPC

Jul 26, 2016—

Central Permit Bureau

Building Inspection · CPB

Aug 15, 2016—

Addendum 1: Foundation, superstructure

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 20, 2017—

Building plan review

Building Inspection · BLDG

Feb 6, 2017—

Building plan review

Building Inspection · BLDG

Feb 8, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Feb 8, 2017—

Building plan review

Building Inspection · BLDG

Feb 17, 2017—

Structural plan approval

Building Inspection · PAD-STR

Feb 17, 2017—

Building plan review

Building Inspection · BLDG

Feb 24, 2017—

Structural plan approval

Building Inspection · PAD-STR

Feb 24, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Feb 24, 2017—

Fire prevention review

Fire Department · SFFD

Feb 24, 2017—

Street use and mapping

Public Works · DPW-BSM

Feb 28, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 1, 2017—

Permit Processing Center

Building Inspection · PPC

Mar 2, 2017—

Central Permit Bureau

Building Inspection · CPB

Mar 15, 2017—

Addendum 2: Walk-in cooler specifications

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 2, 2020—

Building plan review

Building Inspection · BLDG

Jan 8, 2020—

Building plan review

Building Inspection · BLDG

Jan 15, 2020—

Structural plan approval

Building Inspection · PAD-STR

Jan 15, 2020—

Structural plan approval

Building Inspection · PAD-STR

Jul 13, 2020—

Permit Processing Center

Building Inspection · PPC

Jul 15, 2020—

Central Permit Bureau

Building Inspection · CPB

Aug 6, 2020—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$30,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Claudio Martonffy

Claudio Martonffy Design

Architect34835
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201508315701 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record