513 08th Av
San Francisco permit 201511132613 · Inner Richmond
Rear addition & partial attic & garage conversion to habitable. (e) kitchen will be remodeled. (n) full & a half bath will be added. (n) stair to garage level. mud room is proposed.
- Filed
- Nov 13, 2015
- Issued
- Dec 9, 2016 (13 months after filing)
- Completed
- Jan 31, 2019 (26 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 13, 2015 | Nov 13, 2015 | — |
Zoning review Planning · CP-ZOC | Nov 13, 2015 | Aug 26, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Jul 6, 2016 | Aug 26, 2016 | — |
Building plan review Building Inspection · BLDG | Aug 29, 2016 | Sep 19, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2016 | Sep 15, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 27, 2016 | Nov 4, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Nov 4, 2016 | Nov 14, 2016 | — |
Zoning review Planning · CP-ZOC | Nov 14, 2016 | Nov 23, 2016 | — |
Permit Processing Center Building Inspection · PPC | Nov 28, 2016 | Nov 28, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Nov 28, 2016 | Dec 9, 2016 | — |
Addendum 1: Struct,arch,t24,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 9, 2016 | Dec 9, 2016 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2016 | Dec 16, 2016 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 12, 2016 | Jan 25, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2017 | Feb 8, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 26, 2017 | Jan 27, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2017 | Feb 22, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 23, 2017 | Feb 23, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2017 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $175,000
| Name | Role | License on permit |
|---|---|---|
| Jeff Alan Gard Jeff Alan Gard | Architect | C-30906 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025