2575 Marin St
San Francisco permit 201511233305 · Bayview Hunters Point
Demo of (e) entry door & exterior windows; (n) storefront entry & (n) aluminum windows, replace in kind; (n) stand alone 2 story office bldg, (n) load bearing & non-load bearing partitions, 3 (n) ada compliant bathrooms & 1 drinking fountain
- Filed
- Nov 23, 2015
- Issued
- Dec 17, 2015 (within 1 month of filing)
- Completed
- May 19, 2016 (5 months after issuance)
- Review stops
- 9 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Nov 23, 2015 | Nov 23, 2015 | — |
Zoning review Planning · CP-ZOC | Nov 23, 2015 | Nov 23, 2015 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 23, 2015 | Nov 23, 2015 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 24, 2015 | Nov 24, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Nov 24, 2015 | Nov 24, 2015 | — |
Building plan review Building Inspection · BLDG | Nov 24, 2015 | Dec 7, 2015 | — |
Fire prevention review Fire Department · SFFD | Dec 7, 2015 | Dec 9, 2015 | — |
Permit Processing Center Building Inspection · PPC | Dec 9, 2015 | Dec 9, 2015 | — |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2015 | Dec 17, 2015 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $848,000
| Name | Role | License on permit |
|---|---|---|
| Michael J Wilk | Architect | C-29682 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026