1514 25th Av
San Francisco permit 201512175343 · Sunset/Parkside
1st floor: bathroom remodel & addition of bedroom & storage in garage. 2nd floor: kitchen & bathroom remodel. 3rd floor: addition with new kitchen & bathroom. remove (e) stair & add new stair to 3rd floor.
- Filed
- Dec 17, 2015
- Issued
- Sep 29, 2016 (9 months after filing)
- Completed
- Not completed yet
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 17, 2015 | Dec 17, 2015 | — |
Zoning review Planning · CP-ZOC | Dec 17, 2015 | Jul 13, 2016 | — |
Planning neighborhood notice Planning · CP-NP | May 24, 2016 | Jul 13, 2016 | — |
Development fee collection Building Inspection · DFCU | Jul 13, 2016 | Sep 16, 2016 | — |
Building plan review Building Inspection · BLDG | Jul 14, 2016 | Sep 6, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Aug 19, 2016 | Aug 26, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2016 | Sep 15, 2016 | — |
Permit Processing Center Building Inspection · PPC | Sep 15, 2016 | Sep 16, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Sep 16, 2016 | Sep 29, 2016 | — |
Addendum 1: Struct,arch,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 29, 2016 | Sep 29, 2016 | — |
Building plan review Building Inspection · BLDG | Sep 29, 2016 | Nov 15, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2016 | Dec 19, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Nov 17, 2016 | Jan 23, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2016 | Nov 23, 2016 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2017 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 30, 2017 | Jan 30, 2017 | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $350,000
| Name | Role | License on permit |
|---|---|---|
| Baek Young Ahn Baek Young Ahn Architect | Architect | C19749 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2008