686 Arkansas St #0
San Francisco permit 201601217617 · Potrero Hill
Construct new roof deck (less than 500 sq ft), new glass guardrail at street facing side, a new steel guardrail & spiral stair for roof access. 1 unit has access only
- Filed
- Jan 21, 2016
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 8 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jan 21, 2016 | Jan 21, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Feb 2, 2016 | Feb 2, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 2, 2016 | Jan 3, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Sep 14, 2017 | Jan 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 5, 2023 | Mar 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2023 | Mar 20, 2023 | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $60,000
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clifford Anderson | Architect | C31274 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2021