365 Day St
San Francisco permit 201601268003 · Noe Valley
New seismic upgrade foundation throughout. renovate kitchen & bath @ main level. expand upper level to add new master bedroom & bath plus additional bathroom. renovate garage to convert partial livable space. new communicating stair between all levels.
- Filed
- Jan 26, 2016
- Issued
- May 3, 2017 (15 months after filing)
- Completed
- Oct 1, 2018 (17 months after issuance)
- Review stops
- 16 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 26, 2016 | Jan 26, 2016 | — |
Zoning review Planning · CP-ZOC | Jan 26, 2016 | Jan 5, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Nov 3, 2016 | Jan 5, 2017 | — |
Building plan review Building Inspection · BLDG | Jan 6, 2017 | Jan 27, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 27, 2017 | Feb 1, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2017 | Feb 15, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 15, 2017 | Feb 15, 2017 | — |
Development fee collection Building Inspection · DFCU | Feb 15, 2017 | Feb 15, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2017 | May 3, 2017 | — |
Addendum 1: Arch, stru, mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2017 | May 3, 2017 | — |
Building plan review Building Inspection · BLDG | May 3, 2017 | Jun 12, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2017 | Aug 3, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jun 28, 2017 | Aug 8, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 14, 2017 | Jul 17, 2017 | — |
Permit Processing Center Building Inspection · PPC | Aug 8, 2017 | Aug 8, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2017 | Aug 11, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $488,000
| Name | Role | License on permit |
|---|---|---|
| Gary Clay Head Gary Head & Le Vu | Architect | C34982 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2011