62 Allston Wy
San Francisco permit 201602109230 · West of Twin Peaks
Voluntary strengthening demo (e) interior stair add new interior stair for future chair lift add lower bthrm. relocate (e) interior utilities, add windows, replace windows, relocate garage dor. add french drain for site drainage
- Filed
- Feb 10, 2016
- Issued
- Jun 15, 2016 (4 months after filing)
- Completed
- May 1, 2018 (23 months after issuance)
- Review stops
- 25 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 12, 2016 | Feb 12, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 12, 2016 | Apr 13, 2016 | — |
Building plan review Building Inspection · BLDG | Apr 12, 2016 | May 12, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2016 | May 9, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2016 | May 16, 2016 | — |
Street use and mapping Public Works · DPW-BSM | May 16, 2016 | May 23, 2016 | — |
Zoning review Planning · CP-ZOC | May 23, 2016 | May 24, 2016 | — |
Permit Processing Center Building Inspection · PPC | May 25, 2016 | May 25, 2016 | — |
Central Permit Bureau Building Inspection · CPB | May 25, 2016 | Jun 15, 2016 | — |
Addendum 1: Struc, arch, mech, t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 15, 2016 | Jun 15, 2016 | — |
Building plan review Building Inspection · BLDG | Jun 15, 2016 | Jul 6, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2016 | Aug 31, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Jul 14, 2016 | Jul 26, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 27, 2016 | Jul 28, 2016 | — |
Building plan review Building Inspection · BLDG | Aug 31, 2016 | Sep 27, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2016 | Sep 28, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2016 | Oct 3, 2016 | — |
Permit Processing Center Building Inspection · PPC | Oct 5, 2016 | Oct 5, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Oct 5, 2016 | Jan 27, 2017 | — |
Building plan review Building Inspection · BLDG | Jan 27, 2017 | Jan 27, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2017 | Jan 31, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 31, 2017 | Feb 2, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 2, 2017 | Feb 3, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 6, 2017 | Feb 6, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 6, 2017 | Apr 14, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Gary Clay Head Gary Head & Le Vu | Architect | C34982 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022