400 Bay St
San Francisco permit 201602129550 · North Beach
To erect 4 stories of 13 dwelling units, with roof deck
- Filed
- Feb 12, 2016
- Issued
- Dec 30, 2016 (11 months after filing)
- Completed
- Not completed yet
- Review stops
- 69 stops across 7 departments
- Comments issued
- 12 times, by Building Inspection, Public Health, Permit Center
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 22, 2016 | Feb 22, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2016 | Mar 4, 2016 | — |
Building plan review Building Inspection · BLDG | Mar 4, 2016 | Dec 9, 2016 | — |
Fire prevention review Fire Department · SFFD | Apr 7, 2016 | Nov 14, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Apr 22, 2016 | Dec 22, 2016 | — |
Zoning review Planning · CP-ZOC | Nov 15, 2016 | Dec 8, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2016 | Dec 15, 2016 | — |
Development fee collection Building Inspection · DFCU | Dec 23, 2016 | Dec 23, 2016 | — |
Permit Processing Center Building Inspection · PPC | Dec 23, 2016 | Dec 23, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Dec 23, 2016 | Dec 30, 2016 | — |
Addendum 1: Excavation,shoring (withdrawn)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 9, 2018 | Mar 9, 2018 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2018 | Sep 24, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2018 | Mar 1, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 24, 2018 | Oct 9, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 4, 2019 | Apr 8, 2019 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 8, 2019 | Jul 1, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jan 31, 2025 | Jan 31, 2025 | Issued Comments |
Public Health HEALTH-MH | Feb 3, 2025 | Feb 3, 2025 | Issued Comments |
Public Health HEALTH-MH | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Addendum 2: 2) foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 25, 2018 | Apr 25, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2018 | Jun 14, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2018 | Nov 26, 2018 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2018 | Oct 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 27, 2018 | Oct 29, 2025 | — |
Central Permit Bureau Building Inspection · CPB | Oct 16, 2025 | Oct 16, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 16, 2025 | Oct 29, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 28, 2025 | Jul 17, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Nov 17, 2025 | Nov 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 23, 2025 | Feb 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 23, 2025 | Dec 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 21, 2026 | Feb 2, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 6, 2026 | May 29, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2026 | May 11, 2026 | Approved |
Permit Center Permit Center · PERMIT-CTR | Jun 15, 2026 | Jul 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Jun 17, 2026 | Jul 13, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 17, 2026 | Jul 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 8, 2026 | Jul 8, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 8, 2026 | Jul 13, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 8, 2026 | Jul 13, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jul 8, 2026 | Jul 10, 2026 | Not Applicable |
Street use and mapping Public Works · DPW-BSM | Jul 8, 2026 | Jul 13, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 13, 2026 | Jul 13, 2026 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 17, 2026 | Jul 21, 2026 | Administrative |
Addendum 3: 3) superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 17, 2025 | Oct 27, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2026 | Jun 29, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 1, 2026 | Jul 6, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 6, 2026 | Aug 24, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 6, 2026 | Aug 24, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 6, 2026 | Jul 14, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jul 6, 2026 | In progress | — |
Building plan review Building Inspection · BLDG | Sep 29, 2026 | Oct 20, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 29, 2026 | Oct 20, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 7: 1) architectural/mep/civic landscape/mmrp
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 14, 2026 | Aug 3, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 3, 2026 | In progress | In Progress |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Rev1 to issued addendum 2 (foundation)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Oct 1, 2026 | Oct 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 26, 2026 | Oct 26, 2026 | Administrative |
Address verification Building Inspection · ADDR | Oct 26, 2026 | In progress | — |
Zoning review Planning · CP-ZOC | Oct 26, 2026 | Oct 29, 2026 | Not Applicable |
Building plan review Building Inspection · BLDG | Oct 26, 2026 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Oct 26, 2026 | In progress | — |
Fire prevention review Fire Department · SFFD | Oct 26, 2026 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Oct 26, 2026 | Oct 27, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 26, 2026 | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $4,154,500
| Name | Role | License on permit |
|---|---|---|
| Chi-Wing Wong Collaborate Design Group | Architect | C29630 |
| Salvatore Paul Italiano Spi Consulting Engineers | Engineer | C34845 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026