345 06th St
San Francisco permit 201602179763 · South of Market
To erect 9-story, 102 dwelling units apartment, parking, retail, mix use building. n/a for maher ordinance no.155-13.
- Filed
- Feb 17, 2016
- Issued
- Apr 5, 2017 (14 months after filing)
- Completed
- Nov 3, 2020 (43 months after issuance)
- Review stops
- 50 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 14 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 17, 2016 | Feb 17, 2016 | — |
Zoning review Planning · CP-ZOC | Feb 17, 2016 | Dec 23, 2016 | — |
Building plan review Building Inspection · BLDG | Dec 27, 2016 | Jan 4, 2017 | — |
Fire prevention review Fire Department · SFFD | Jan 4, 2017 | Jan 20, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 20, 2017 | Jan 23, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2017 | Feb 9, 2017 | — |
Public health review Public Health · HEALTH | Feb 10, 2017 | Mar 1, 2017 | — |
Zoning review Planning · CP-ZOC | Mar 1, 2017 | Mar 3, 2017 | — |
Development fee collection Building Inspection · DFCU | Mar 7, 2017 | Mar 27, 2017 | — |
Permit Processing Center Building Inspection · PPC | Mar 27, 2017 | Mar 27, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2017 | Apr 5, 2017 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 18, 2017 | Aug 18, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2017 | Aug 30, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2017 | Nov 28, 2017 | — |
Permit Processing Center Building Inspection · PPC | Nov 30, 2017 | Nov 30, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Nov 30, 2017 | Dec 7, 2017 | — |
Addendum 2: Superstructure framing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 18, 2017 | Aug 18, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 18, 2017 | Aug 30, 2017 | — |
Permit Processing Center Building Inspection · PPC | Aug 30, 2017 | Aug 30, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2017 | Sep 13, 2017 | — |
Addendum 3: Tower crane
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 13, 2017 | Dec 13, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 13, 2017 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Sep 29, 2020 | Sep 29, 2020 | — |
Addendum 4: Architectural plan.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 6, 2017 | Dec 6, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 6, 2017 | Jan 8, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 8, 2018 | Oct 30, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2018 | Jan 7, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2018 | Apr 18, 2018 | — |
Public health review Public Health · HEALTH | Oct 30, 2018 | Nov 1, 2018 | — |
Zoning review Planning · CP-ZOC | Jan 8, 2019 | Apr 4, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 5, 2019 | Apr 5, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 5, 2019 | Apr 9, 2019 | — |
Addendum 5: Mechanical & electrical plan.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 16, 2018 | Nov 16, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 19, 2018 | Mar 21, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Dec 20, 2018 | Mar 22, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2019 | Mar 7, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 25, 2019 | Mar 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 25, 2019 | Mar 26, 2019 | — |
Addendum 6: Fire sprinkler.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 11, 2019 | Apr 11, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 11, 2019 | May 30, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 31, 2019 | May 31, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 31, 2019 | Jun 5, 2019 | — |
Addendum 7: Fire alarm.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 8, 2020 | Jun 8, 2020 | — |
Fire prevention review Fire Department · SFFD | Jun 8, 2020 | Jun 17, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 17, 2020 | Jun 17, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2020 | Aug 22, 2020 | — |
Addendum 8: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 11, 2020 | Jun 11, 2020 | — |
Fire prevention review Fire Department · SFFD | Jun 11, 2020 | Jul 6, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jul 14, 2020 | Jul 14, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jul 14, 2020 | Aug 22, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $6,000,000
| Name | Role | License on permit |
|---|---|---|
| Siavash Tahbazof Sia Consulting Corporation | Engineer | C38827 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026