Horizontal addition: expand (e) bldg towards rear yard. vertical addition: build a new 2/fl over the (e) main floor. minor excavation to move back rear patio. build new and repair (e) retaining wall to ensure soil stability. seismic structural upgrade.
- Filed
- Mar 4, 2016
- Issued
- Aug 11, 2017 (17 months after filing)
- Completed
- Mar 20, 2019 (19 months after issuance)
- Review stops
- 21 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Mar 4, 2016 | Mar 4, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2016 | Mar 11, 2016 | — |
Zoning review Planning · CP-ZOC | Mar 11, 2016 | Jul 3, 2017 | — |
Planning neighborhood notice Planning · CP-NP | May 19, 2017 | Jun 30, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 5, 2017 | Jul 10, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2017 | Jul 18, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2017 | Jul 28, 2017 | — |
Development fee collection Building Inspection · DFCU | Jul 31, 2017 | Jul 31, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jul 31, 2017 | Jul 31, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2017 | Aug 11, 2017 | — |
Addendum 1: Foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2017 | Aug 17, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2017 | Aug 22, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2017 | Sep 5, 2017 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2017 | Sep 7, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Sep 7, 2017 | Sep 19, 2017 | — |
Addendum 2: Architectural/t24/mechanical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2017 | Oct 25, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 25, 2017 | Nov 1, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 7, 2017 | Nov 7, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2017 | Nov 8, 2017 | — |
Permit Processing Center Building Inspection · PPC | Nov 8, 2017 | Nov 8, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Nov 8, 2017 | Nov 10, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $479,482
| Name | Role | License on permit |
|---|---|---|
| Winnie Hing-Wan Tam Winnie Tam | Architect | C31166 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025