666 Madrid St
San Francisco permit 201603071402 · Excelsior
To comply with n.o.v #200682015 #200877593,#200884232, construct retaining walls in bsement to strenghten (e) concorete footing/retaining walls. construct rear addtiion: complete interior remodel. relocate gas meter & upgrade electrical panel.
- Filed
- Mar 7, 2016
- Issued
- Nov 3, 2016 (8 months after filing)
- Completed
- Aug 2, 2018 (21 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Mar 7, 2016 | Mar 7, 2016 | — |
Apartment and hotel inspection Building Inspection · HIS | Mar 7, 2016 | Mar 7, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2016 | Mar 23, 2016 | — |
Zoning review Planning · CP-ZOC | Mar 23, 2016 | Sep 22, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Aug 3, 2016 | Sep 21, 2016 | — |
Building plan review Building Inspection · BLDG | Sep 23, 2016 | Sep 30, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Sep 30, 2016 | Oct 5, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2016 | Oct 20, 2016 | — |
Permit Processing Center Building Inspection · PPC | Nov 1, 2016 | Nov 1, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Nov 1, 2016 | Nov 3, 2016 | — |
Addendum 1: Struct,arch,t24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 3, 2016 | Nov 3, 2016 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2016 | Dec 1, 2016 | — |
Building plan review Building Inspection · BLDG | Nov 3, 2016 | Nov 9, 2016 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 1, 2016 | Jan 25, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Dec 22, 2016 | Feb 15, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 30, 2016 | Jan 3, 2017 | — |
Permit Processing Center Building Inspection · PPC | Feb 15, 2017 | Feb 15, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2017 | Mar 15, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $226,100
| Name | Role | License on permit |
|---|---|---|
| Choi-Keung Anthony Chau Anthony Chau & Partners Llc | Architect | C30909 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026