302 Silver Av
San Francisco permit 201603152080 · Excelsior
To erect 5 stories, 2 basement, residential care for the elderly building.
- Filed
- Mar 15, 2016
- Issued
- Nov 21, 2016 (8 months after filing)
- Completed
- Feb 25, 2021 (51 months after issuance)
- Review stops
- 77 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 17 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 15, 2016 | Mar 15, 2016 | — |
Zoning review Planning · CP-ZOC | Mar 30, 2016 | Jul 11, 2016 | — |
Building plan review Building Inspection · BLDG | Jul 12, 2016 | Nov 10, 2016 | — |
Fire prevention review Fire Department · SFFD | Sep 26, 2016 | Nov 10, 2016 | — |
Street use and mapping Public Works · DPW-BSM | Nov 10, 2016 | Nov 15, 2016 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 16, 2016 | Nov 16, 2016 | — |
Public health review Public Health · HEALTH | Nov 16, 2016 | Nov 17, 2016 | — |
Development fee collection Building Inspection · DFCU | Nov 16, 2016 | Nov 16, 2016 | — |
Zoning review Planning · CP-ZOC | Nov 17, 2016 | Nov 18, 2016 | — |
Permit Processing Center Building Inspection · PPC | Nov 18, 2016 | Nov 18, 2016 | — |
Central Permit Bureau Building Inspection · CPB | Nov 18, 2016 | Nov 21, 2016 | — |
Addendum 1: Foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 29, 2016 | Dec 29, 2016 | — |
Building plan review Building Inspection · BLDG | Dec 29, 2016 | Apr 3, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2017 | Apr 12, 2017 | — |
Permit Processing Center Building Inspection · PPC | Apr 13, 2017 | Apr 13, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Apr 13, 2017 | Jun 21, 2017 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2017 | Jun 30, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jul 3, 2017 | Jul 3, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jul 3, 2017 | Aug 14, 2017 | — |
Addendum 2: Superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 13, 2017 | Mar 13, 2017 | — |
Building plan review Building Inspection · BLDG | Mar 14, 2017 | Jun 26, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jun 26, 2017 | Jun 26, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jun 26, 2017 | Aug 14, 2017 | — |
Addendum 3: Mech,elec,plumbing,& arch
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 18, 2017 | Aug 18, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 21, 2017 | Nov 9, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 3, 2017 | Nov 15, 2018 | — |
Electrical plan review Building Inspection · MECH-E | Dec 13, 2017 | Dec 3, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 22, 2018 | Dec 12, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2018 | Dec 27, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2018 | Jun 26, 2018 | — |
Zoning review Planning · CP-ZOC | Dec 28, 2018 | Feb 15, 2019 | — |
Public health review Public Health · HEALTH | Feb 20, 2019 | Mar 4, 2019 | — |
Permit Processing Center Building Inspection · PPC | Feb 20, 2019 | Mar 18, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 11, 2019 | Mar 12, 2019 | — |
Zoning review Planning · CP-ZOC | Mar 12, 2019 | Mar 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2019 | Mar 19, 2019 | — |
Addendum 4: Pre-fab stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 13, 2018 | Aug 13, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 13, 2018 | Dec 12, 2018 | — |
Fire prevention review Fire Department · SFFD | Aug 27, 2018 | Oct 19, 2018 | — |
Permit Processing Center Building Inspection · PPC | Dec 12, 2018 | Dec 12, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2018 | Jan 4, 2019 | — |
Addendum 5: Erccs system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 15, 2019 | Mar 15, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 15, 2019 | May 18, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 20, 2019 | May 20, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 20, 2019 | May 21, 2019 | — |
Addendum 6: Fire protection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 26, 2019 | Mar 26, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 26, 2019 | Apr 17, 2019 | — |
Fire prevention review Fire Department · SFFD | May 14, 2019 | May 14, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 14, 2019 | May 14, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 14, 2019 | May 17, 2019 | — |
Addendum 7: Fire alarm & two way comm system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 1, 2019 | Oct 1, 2019 | — |
Fire prevention review Fire Department · SFFD | Oct 1, 2019 | Feb 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 3, 2020 | Feb 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2020 | Feb 4, 2020 | — |
Addendum 8: Window washing system
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 9: Pool
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 10: Fuel & generator (stand-by)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 16, 2019 | Apr 16, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 16, 2019 | May 14, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2019 | Jun 4, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Jun 4, 2019 | Nov 18, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 18, 2019 | Nov 8, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2019 | Nov 19, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 19, 2019 | Nov 27, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2019 | Dec 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | Dec 9, 2019 | Dec 9, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2019 | Dec 10, 2019 | — |
Addendum 11: Canopy hoods (commercial kitchen)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 12: Walk-in cold storage
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 13: Cold-framed framing
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 19, 2019 | Mar 19, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 19, 2019 | Jun 10, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Apr 8, 2019 | Apr 9, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 10, 2019 | Jun 10, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 10, 2019 | Jun 11, 2019 | — |
Addendum 14: Firestopping
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 15: Glazed aluminum curtain walls
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 16: Aluminum window wall
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Addendum 17: Landscape
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 10, 2020 | Mar 10, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $67,000,000
| Name | Role | License on permit |
|---|---|---|
| Allen Scott Nudel Forell / Elsesser Engineers | Engineer | 4508 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Oct 2026