929 Diamond St
San Francisco permit 201603303516 · Noe Valley
Adding garage; creating first floor unit, inclunding 2 bed/bath, living + kitchen. enlarging/renovating unit on second & third floors. adding kitchen and bath.
- Filed
- Mar 30, 2016
- Issued
- Apr 5, 2021 (60 months after filing)
- Completed
- Not completed yet
- Review stops
- 19 stops across 4 departments
- Comments issued
- None
- Put on hold
- 8 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 7, 2016 | Apr 7, 2016 | — |
Zoning review Planning · CP-ZOC | Apr 7, 2016 | Apr 25, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Sep 19, 2018 | Oct 3, 2018 | — |
Planning discretionary review Planning · CP-DR | Nov 14, 2018 | Feb 21, 2019 | — |
Building plan review Building Inspection · BLDG | Apr 25, 2019 | Jul 12, 2019 | — |
Street use and mapping Public Works · DPW-BSM | May 28, 2019 | Jul 15, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2019 | Jun 7, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jul 16, 2019 | Aug 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2019 | Aug 19, 2019 | — |
Zoning review Planning · CP-ZOC | Aug 19, 2019 | Aug 22, 2019 | — |
Development fee collection Building Inspection · DFCU | Aug 23, 2019 | Aug 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2019 | Apr 5, 2021 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 15, 2021 | Jun 21, 2021 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2021 | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2021 | In progress | — |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2021 | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 10, 2021 | Dec 10, 2021 | — |
Permit Processing Center Building Inspection · PPC | Jul 2, 2024 | Jul 2, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $800,000
| Name | Role | License on permit |
|---|---|---|
| Michael H Mullin Michael Mullin Architect | Architect | C25447 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025