663 Mangels Av
San Francisco permit 201605207955 · West of Twin Peaks
Relocate entry door to align w/face of bldg; replace (e) new windows, bldg new entry porch w/bracketed roof, landing, steps, widen (e) garage door, (n) int double pocket door, restucco entire front, (n) ret.wall @ porch/driveway.
- Filed
- May 20, 2016
- Issued
- May 22, 2017 (12 months after filing)
- Completed
- Aug 7, 2019 (27 months after issuance)
- Review stops
- 15 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Zoning review Planning · CP-ZOC | Feb 24, 2017 | Feb 24, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2017 | Mar 27, 2017 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2017 | Apr 4, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2017 | Apr 13, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2017 | Apr 19, 2017 | — |
Permit Processing Center Building Inspection · PPC | Apr 20, 2017 | Apr 20, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Apr 20, 2017 | May 22, 2017 | — |
Addendum 1: Struc, arch, mech, t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 22, 2017 | May 22, 2017 | — |
Building plan review Building Inspection · BLDG | May 22, 2017 | May 23, 2017 | — |
Zoning review Planning · CP-ZOC | May 23, 2017 | Jun 2, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2017 | May 23, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2017 | Jun 20, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2017 | Jun 27, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jun 28, 2017 | Jun 28, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jun 28, 2017 | Apr 4, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $75,000
| Name | Role | License on permit |
|---|---|---|
| Laurie Jo Erickson Erickson Zebroski Design Group | Architect | C24082 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022