300 16th St

San Francisco permit 201606149949 · Mission Bay

New buildingFull plan reviewComplete
Street view · Sep 2026
Google Street View of 300 16th St, Sep 2026
Scope of work
As written on the permit application.

Construct (n) professional sports arena: includes gate house, theatre/auditorium, parking garage, team offices, gymnasiums, restaurants & retail

Timeline
Key dates from the city record.
Filed
Jun 14, 2016
Issued
Apr 11, 2017 (10 months after filing)
Completed
Oct 19, 2020 (42 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
161 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
24 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 14, 2016—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Apr 3, 2017—

Fire prevention review

Fire Department · SFFD

Mar 30, 2017—

Structural plan approval

Building Inspection · PAD-STR

Apr 3, 2017—

Development fee collection

Building Inspection · DFCU

Apr 10, 2017—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Street use and mapping

Public Works · DPW-BSM

Mar 31, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 3, 2017—

Redevelopment review

Redevelopment · REDEV

Apr 6, 2017—

Public health review

Public Health · HEALTH

Apr 7, 2017—

Permit Processing Center

Building Inspection · PPC

Apr 10, 2017—

Central Permit Bureau

Building Inspection · CPB

Apr 11, 2017—

Addendum 1: Foundation

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 5, 2017—

Building plan review

Building Inspection · BLDG

Jun 9, 2017—

Street use and mapping

Public Works · DPW-BSM

Jun 12, 2017—

Development fee collection

Building Inspection · DFCU

Jun 12, 2017—

Redevelopment review

Redevelopment · REDEV

Jun 13, 2017—

Permit Processing Center

Building Inspection · PPC

Jun 14, 2017—

Central Permit Bureau

Building Inspection · CPB

Jun 14, 2017—

Addendum 2: Substructure/superstructure (through plaza)

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 20, 2017—

Building plan review

Building Inspection · BLDG

Sep 22, 2017—

Street use and mapping

Public Works · DPW-BSM

Sep 25, 2017—

Redevelopment review

Redevelopment · REDEV

Sep 28, 2017—

Permit Processing Center

Building Inspection · PPC

Sep 29, 2017—

Central Permit Bureau

Building Inspection · CPB

Sep 29, 2017—

Addendum 3: Superstructure (arena above plaza)

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 11, 2017—

Building plan review

Building Inspection · BLDG

Nov 17, 2017—

Street use and mapping

Public Works · DPW-BSM

Nov 27, 2017—

Permit Processing Center

Building Inspection · PPC

Nov 28, 2017—

Central Permit Bureau

Building Inspection · CPB

Nov 29, 2017—

Redevelopment review

Redevelopment · REDEV

Dec 21, 2017—

Permit Processing Center

Building Inspection · PPC

Jan 18, 2018—

Central Permit Bureau

Building Inspection · CPB

Jan 18, 2018—

Addendum 4: Arch,mep,landscape & seismic instrumentation (arena/garage)

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 13, 2017—

Building plan review

Building Inspection · BLDG

Oct 22, 2018—

Fire prevention review

Fire Department · SFFD

Jan 24, 2019—

Mechanical and energy plan review

Building Inspection · MECH

Mar 25, 2019—

Electrical plan review

Building Inspection · MECH-E

Oct 26, 2018—

Plumbing plan check

Building Inspection · PID-PC

Oct 23, 2018—

Public health review

Public Health · HEALTH

Jan 9, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 31, 2018—

Street use and mapping

Public Works · DPW-BSM

Nov 8, 2018—

Building plan review

Building Inspection · BLDG

Jan 18, 2019—

Redevelopment review

Redevelopment · REDEV

Mar 21, 2019—

Building plan review

Building Inspection · BLDG

Mar 26, 2019—

Permit Processing Center

Building Inspection · PPC

Mar 26, 2019—

Central Permit Bureau

Building Inspection · CPB

Mar 27, 2019—

Addendum 5: Concrete seating pullout pre-cast & steel stairs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 6, 2017—

Building plan review

Building Inspection · BLDG

Apr 18, 2018—

Structural plan approval

Building Inspection · PAD-STR

May 8, 2018—

Fire prevention review

Fire Department · SFFD

May 24, 2018—

Permit Processing Center

Building Inspection · PPC

May 25, 2018—

Central Permit Bureau

Building Inspection · CPB

May 29, 2018—

Redevelopment review

Redevelopment · REDEV

May 31, 2018—

Permit Processing Center

Building Inspection · PPC

May 31, 2018—

Central Permit Bureau

Building Inspection · CPB

Jun 1, 2018—

Addendum 6: Fire sprinkler

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 29, 2017—

Fire prevention review

Fire Department · SFFD

Jan 31, 2019—

Permit Processing Center

Building Inspection · PPC

Feb 1, 2019—

Central Permit Bureau

Building Inspection · CPB

Feb 1, 2019—

Addendum 7: Fire alarm & emergency elevator lobby communicaton

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 20, 2019—

Fire prevention review

Fire Department · SFFD

May 28, 2019—

Permit Processing Center

Building Inspection · PPC

May 28, 2019—

Central Permit Bureau

Building Inspection · CPB

May 29, 2019—

Addendum 8: Fuel oil & generator

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 1, 2018—

Building plan review

Building Inspection · BLDG

Oct 19, 2018—

Mechanical and energy plan review

Building Inspection · MECH

Dec 17, 2018—

Fire prevention review

Fire Department · SFFD

Jan 4, 2019—

Structural plan approval

Building Inspection · PAD-STR

Nov 1, 2018—

Building plan review

Building Inspection · BLDG

Nov 1, 2018—

Electrical plan review

Building Inspection · MECH-E

Dec 13, 2018—

Building plan review

Building Inspection · BLDG

Jan 8, 2019—

Permit Processing Center

Building Inspection · PPC

Jan 9, 2019—

Structural plan approval

Building Inspection · PAD-STR

Jan 8, 2019—

Central Permit Bureau

Building Inspection · CPB

Jan 9, 2019—

Addendum 9: Window washing system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 14, 2018—

Building plan review

Building Inspection · BLDG

Apr 11, 2019—

Building plan review

Building Inspection · BLDG

Apr 12, 2019—

Building plan review

Building Inspection · BLDG

Apr 15, 2019—

Fire prevention review

Fire Department · SFFD

Apr 12, 2019—

Structural plan approval

Building Inspection · PAD-STR

May 14, 2019—

Permit Processing Center

Building Inspection · PPC

May 14, 2019—

Central Permit Bureau

Building Inspection · CPB

May 15, 2019—

Addendum 10: Fire fighter elevator

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 28, 2019—

Fire prevention review

Fire Department · SFFD

Jul 26, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 29, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 29, 2019—

Addendum 11: Errcs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 18, 2018—

Fire prevention review

Fire Department · SFFD

Mar 24, 2019—

Permit Processing Center

Building Inspection · PPC

Mar 25, 2019—

Central Permit Bureau

Building Inspection · CPB

Mar 25, 2019—

Addendum 12: Retractable seating system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 19, 2018—

Building plan review

Building Inspection · BLDG

Feb 1, 2019—

Structural plan approval

Building Inspection · PAD-STR

Dec 19, 2018—

Structural plan approval

Building Inspection · PAD-STR

Apr 11, 2019—

Fire prevention review

Fire Department · SFFD

Apr 13, 2019—

Permit Processing Center

Building Inspection · PPC

Apr 15, 2019—

Central Permit Bureau

Building Inspection · CPB

Apr 15, 2019—

Addendum 13: Arena roof & superstructure

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 27, 2017—

Building plan review

Building Inspection · BLDG

May 17, 2018—

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2018—

Redevelopment review

Redevelopment · REDEV

Jun 19, 2018—

Permit Processing Center

Building Inspection · PPC

Jun 19, 2018—

Central Permit Bureau

Building Inspection · CPB

Jun 20, 2018—

Addendum 14: Exterior enclosure.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 5, 2018—

Building plan review

Building Inspection · BLDG

Mar 8, 2019—

Fire prevention review

Fire Department · SFFD

May 14, 2019—

Redevelopment review

Redevelopment · REDEV

May 30, 2019—

Permit Processing Center

Building Inspection · PPC

Jun 3, 2019—

Central Permit Bureau

Building Inspection · CPB

Jun 3, 2019—

Addendum 15: Landscape on plaza & street level

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 14, 2019—

Building plan review

Building Inspection · BLDG

May 20, 2019—

Fire prevention review

Fire Department · SFFD

May 3, 2019—

Street use and mapping

Public Works · DPW-BSM

May 9, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

May 9, 2019—

Fire prevention review

Fire Department · SFFD

May 24, 2019—

Street use and mapping

Public Works · DPW-BSM

May 28, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

May 29, 2019—

Redevelopment review

Redevelopment · REDEV

Jul 11, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 12, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2019—

Addendum 16: Superstructure for gatehouse

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 1, 2018—

Building plan review

Building Inspection · BLDG

Oct 19, 2018—

Permit Processing Center

Building Inspection · PPC

Oct 23, 2018—

Central Permit Bureau

Building Inspection · CPB

Oct 24, 2018—

Addendum 17: Signage

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 7, 2019—

Building plan review

Building Inspection · BLDG

Jul 24, 2019—

Fire prevention review

Fire Department · SFFD

Jul 24, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 29, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 29, 2019—

Addendum 18: Stairs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 1, 2018—

Building plan review

Building Inspection · BLDG

Mar 21, 2019—

Fire prevention review

Fire Department · SFFD

Apr 24, 2019—

Permit Processing Center

Building Inspection · PPC

Apr 26, 2019—

Central Permit Bureau

Building Inspection · CPB

Apr 29, 2019—

Addendum 19: Tension mesh

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 4, 2019—

Building plan review

Building Inspection · BLDG

Apr 5, 2019—

Permit Processing Center

Building Inspection · PPC

Apr 5, 2019—

Central Permit Bureau

Building Inspection · CPB

Apr 8, 2019—

Addendum 20: Trellis system & neolith framing system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 30, 2019—

Building plan review

Building Inspection · BLDG

May 2, 2019—

Structural plan approval

Building Inspection · PAD-STR

Jun 13, 2019—

Fire prevention review

Fire Department · SFFD

Jun 24, 2019—

Permit Processing Center

Building Inspection · PPC

Jun 27, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 2, 2019—

Addendum 21: Center scoreboad & ribbons

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 11, 2019—

Building plan review

Building Inspection · BLDG

Jul 23, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 23, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 23, 2019—

Addendum 22: Stairs

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 30, 2019—

Building plan review

Building Inspection · BLDG

Jul 10, 2019—

Fire prevention review

Fire Department · SFFD

Jun 27, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 12, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2019—

Addendum 23: Upper bowl masking

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 6, 2019—

Building plan review

Building Inspection · BLDG

Jul 9, 2019—

Fire prevention review

Fire Department · SFFD

Jul 30, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 30, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 30, 2019—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Complete
Estimated cost
$780,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rollie D Childers

Kendal Heaton Associates, Inc.

ArchitectC15472
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201606149949 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record