Scope of work
As written on the permit application.

Construct (n) 11-story office building

Timeline
Key dates from the city record.
Filed
Jun 14, 2016
Issued
Apr 11, 2017 (10 months after filing)
Completed
Jul 24, 2020 (39 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
76 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
13 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 14, 2016—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Fire prevention review

Fire Department · SFFD

Mar 30, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Apr 3, 2017—

Structural plan approval

Building Inspection · PAD-STR

Apr 3, 2017—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Building plan review

Building Inspection · BLDG

Mar 31, 2017—

Street use and mapping

Public Works · DPW-BSM

Mar 31, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 3, 2017—

Redevelopment review

Redevelopment · REDEV

Apr 6, 2017—

Development fee collection

Building Inspection · DFCU

Apr 10, 2017—

Permit Processing Center

Building Inspection · PPC

Apr 10, 2017—

Central Permit Bureau

Building Inspection · CPB

Apr 11, 2017—

Addendum 1: Superstructure

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 11, 2017—

Building plan review

Building Inspection · BLDG

Feb 28, 2018—

Street use and mapping

Public Works · DPW-BSM

Mar 14, 2018—

Redevelopment review

Redevelopment · REDEV

May 10, 2018—

Permit Processing Center

Building Inspection · PPC

May 10, 2018—

Central Permit Bureau

Building Inspection · CPB

May 16, 2018—

Addendum 2: Arch/mep/seismic monitory system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 2, 2017—

Building plan review

Building Inspection · BLDG

Oct 22, 2018—

Mechanical and energy plan review

Building Inspection · MECH

Jan 22, 2019—

Electrical plan review

Building Inspection · MECH-E

Jan 24, 2019—

Fire prevention review

Fire Department · SFFD

Jan 24, 2019—

Street use and mapping

Public Works · DPW-BSM

Feb 6, 2019—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 6, 2019—

Redevelopment review

Redevelopment · REDEV

Apr 11, 2019—

Building plan review

Building Inspection · BLDG

Apr 15, 2019—

Fire prevention review

Fire Department · SFFD

Apr 18, 2019—

Permit Processing Center

Building Inspection · PPC

Apr 18, 2019—

Central Permit Bureau

Building Inspection · CPB

Apr 19, 2019—

Addendum 3: Precast stair assemblies & metal stair

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 18, 2017—

Building plan review

Building Inspection · BLDG

Oct 30, 2018—

Fire prevention review

Fire Department · SFFD

Aug 20, 2018—

Fire prevention review

Fire Department · SFFD

Nov 5, 2018—

Permit Processing Center

Building Inspection · PPC

Nov 5, 2018—

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2018—

Addendum 4: Enclosure, roof screen,metal stud back-up system & curtain wall

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 6, 2018—

Building plan review

Building Inspection · BLDG

Nov 19, 2018—

Fire prevention review

Fire Department · SFFD

Apr 23, 2019—

Building plan review

Building Inspection · BLDG

Nov 19, 2018—

Redevelopment review

Redevelopment · REDEV

May 21, 2019—

Building plan review

Building Inspection · BLDG

Jun 6, 2019—

Permit Processing Center

Building Inspection · PPC

Jun 6, 2019—

Central Permit Bureau

Building Inspection · CPB

Jun 7, 2019—

Addendum 5: Fire protection

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Mar 15, 2018—

Fire prevention review

Fire Department · SFFD

Feb 13, 2019—

Permit Processing Center

Building Inspection · PPC

Feb 13, 2019—

Central Permit Bureau

Building Inspection · CPB

Feb 13, 2019—

Addendum 6: Fire alarm & emergency elevator lobby comm

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 28, 2019—

Fire prevention review

Fire Department · SFFD

May 28, 2019—

Permit Processing Center

Building Inspection · PPC

May 28, 2019—

Central Permit Bureau

Building Inspection · CPB

May 29, 2019—

Addendum 7: Emergency response radio coverage system

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Dec 18, 2018—

Fire prevention review

Fire Department · SFFD

Mar 24, 2019—

Permit Processing Center

Building Inspection · PPC

Mar 25, 2019—

Central Permit Bureau

Building Inspection · CPB

Mar 25, 2019—

Addendum 8: Fire service access elevator

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 28, 2019—

Fire prevention review

Fire Department · SFFD

Jul 26, 2019—

Permit Processing Center

Building Inspection · PPC

Jul 26, 2019—

Central Permit Bureau

Building Inspection · CPB

Jul 29, 2019—

Addendum 9: Fuel oil & generator

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 1, 2018—

Building plan review

Building Inspection · BLDG

Jan 30, 2019—

Mechanical and energy plan review

Building Inspection · MECH

Dec 13, 2018—

Fire prevention review

Fire Department · SFFD

Jan 4, 2019—

Electrical plan review

Building Inspection · MECH-E

Dec 13, 2018—

Structural plan approval

Building Inspection · PAD-STR

Feb 1, 2019—

Building plan review

Building Inspection · BLDG

Feb 5, 2019—

Permit Processing Center

Building Inspection · PPC

Feb 6, 2019—

Central Permit Bureau

Building Inspection · CPB

Feb 6, 2019—

Addendum 10: Window washing

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 13, 2019—

Building plan review

Building Inspection · BLDG

Jul 2, 2019—

Fire prevention review

Fire Department · SFFD

Jul 23, 2019—

Redevelopment review

Redevelopment · REDEV

Aug 8, 2019—

Permit Processing Center

Building Inspection · PPC

Aug 8, 2019—

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2019—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction
Status
Complete
Estimated cost
$87,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Rollie D Childers

Kendal Heaton Associates, Inc.

ArchitectC15472
Sources
Everything on this page comes from public records. Check them yourself.
Permit 201606149954 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record