1500 Mission St
San Francisco permit 201606200387 · Mission
To erect 16 stories, 2 basement, office building & 39 stories, 2 basement, type ia, 550 residential units building. both buildings are over a shared two level subterranean basement parking garage. (r-2,b,a-3,i-4,s-2)
- Filed
- Jun 20, 2016
- Issued
- Oct 3, 2017 (15 months after filing)
- Completed
- Dec 8, 2021 (50 months after issuance)
- Review stops
- 190 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 43 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 20, 2016 | Jun 20, 2016 | — |
Zoning review Planning · CP-ZOC | Jun 20, 2016 | Sep 1, 2017 | — |
Building plan review Building Inspection · BLDG | Jun 24, 2016 | Jul 28, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 24, 2016 | Jul 19, 2017 | — |
Fire prevention review Fire Department · SFFD | Jun 27, 2016 | Jul 27, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 19, 2017 | Aug 17, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Aug 4, 2017 | Aug 8, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 8, 2017 | Aug 16, 2017 | — |
Development fee collection Building Inspection · DFCU | Sep 5, 2017 | Sep 5, 2017 | — |
Permit Processing Center Building Inspection · PPC | Sep 5, 2017 | Sep 5, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Sep 5, 2017 | Oct 3, 2017 | — |
Addendum 1: Foundation-1500 mission & 49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 3, 2017 | Oct 3, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 6, 2017 | Jan 23, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 7, 2017 | Mar 20, 2018 | — |
Permit Processing Center Building Inspection · PPC | Mar 21, 2018 | Mar 21, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Mar 21, 2018 | Mar 21, 2018 | — |
Addendum 2: Superstructure-1500 mission & 49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 3, 2017 | Oct 3, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 10, 2017 | Jul 27, 2018 | — |
Building plan review Building Inspection · BLDG | Jul 27, 2018 | Aug 2, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Aug 2, 2018 | Aug 3, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 3, 2018 | Aug 3, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 3, 2018 | Aug 3, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 3, 2018 | Aug 6, 2018 | — |
Addendum 3: Architectural-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 17, 2017 | Oct 17, 2017 | — |
Fire prevention review Fire Department · SFFD | Oct 17, 2017 | Dec 27, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2017 | Aug 23, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2017 | Nov 26, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 27, 2018 | Jan 28, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 2, 2019 | Jan 3, 2019 | — |
Zoning review Planning · CP-ZOC | Jan 28, 2019 | Feb 15, 2019 | — |
Permit Processing Center Building Inspection · PPC | Feb 15, 2019 | Feb 26, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2019 | Feb 27, 2019 | — |
Addendum 4: Architectural-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Public Utilities Commission review Public Utilities · SFPUC | Mar 27, 2017 | Mar 28, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Dec 4, 2017 | Dec 4, 2017 | — |
Fire prevention review Fire Department · SFFD | Dec 4, 2017 | Dec 27, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2017 | Dec 3, 2018 | — |
Building plan review Building Inspection · BLDG | Dec 4, 2017 | Mar 16, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2018 | Mar 29, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Nov 28, 2018 | Mar 22, 2019 | — |
Zoning review Planning · CP-ZOC | Feb 21, 2019 | Feb 25, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 29, 2019 | Mar 29, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 29, 2019 | Apr 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | Apr 2, 2019 | Apr 2, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Apr 2, 2019 | Apr 2, 2019 | — |
Addendum 5: Mep-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 30, 2018 | Mar 30, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2018 | Apr 10, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2018 | May 11, 2018 | — |
Fire prevention review Fire Department · SFFD | Mar 30, 2018 | May 28, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Apr 11, 2018 | Apr 18, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 28, 2019 | May 29, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 29, 2019 | May 29, 2019 | — |
Addendum 6: Mep-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 31, 2018 | Jan 31, 2018 | — |
Fire prevention review Fire Department · SFFD | Jan 31, 2018 | May 28, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 31, 2018 | Oct 18, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 31, 2018 | Mar 22, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Feb 22, 2018 | Apr 17, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 28, 2019 | May 29, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 29, 2019 | May 29, 2019 | — |
Addendum 7: Fire sprinkler-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 19, 2019 | Mar 19, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 19, 2019 | May 22, 2019 | — |
Fire prevention review Fire Department · SFFD | May 22, 2019 | May 22, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 22, 2019 | May 22, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 22, 2019 | May 24, 2019 | — |
Addendum 8: Fire sprinkler-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 2, 2019 | Apr 2, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 2, 2019 | Apr 17, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 23, 2019 | May 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 23, 2019 | May 24, 2019 | — |
Addendum 9: Stair-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 17, 2018 | Aug 17, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2018 | Aug 31, 2018 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2018 | Mar 1, 2019 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 17, 2018 | Mar 1, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 1, 2019 | Mar 6, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2019 | Mar 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2019 | Mar 8, 2019 | — |
Addendum 10: Stair-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 17, 2018 | Oct 17, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 17, 2018 | Mar 1, 2019 | — |
Fire prevention review Fire Department · SFFD | Mar 1, 2019 | Mar 6, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 7, 2019 | Mar 7, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2019 | Mar 8, 2019 | — |
Addendum 11: Exterior enclosure-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 27, 2018 | Nov 27, 2018 | — |
Building plan review Building Inspection · BLDG | Nov 27, 2018 | Feb 19, 2019 | — |
Zoning review Planning · CP-ZOC | Dec 13, 2018 | Jan 17, 2019 | — |
Fire prevention review Fire Department · SFFD | Jan 17, 2019 | Feb 22, 2019 | — |
Permit Processing Center Building Inspection · PPC | Feb 22, 2019 | Feb 22, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2019 | Feb 22, 2019 | — |
Addendum 12: Exterior enclosure-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 26, 2018 | Jul 26, 2018 | — |
Zoning review Planning · CP-ZOC | Jul 27, 2018 | Jan 29, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 30, 2019 | Feb 15, 2019 | — |
Fire prevention review Fire Department · SFFD | Feb 15, 2019 | May 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 2, 2019 | May 2, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 2, 2019 | May 2, 2019 | — |
Addendum 13: Fire alarm sys,elevator landing,2 way communit-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 19, 2019 | Sep 19, 2019 | — |
Fire prevention review Fire Department · SFFD | Sep 19, 2019 | Oct 2, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 2, 2019 | Oct 2, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2019 | Oct 3, 2019 | — |
Addendum 14: Fire alarm sys,elevator landing,2 way communit-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 15, 2019 | Oct 15, 2019 | — |
Fire prevention review Fire Department · SFFD | Oct 16, 2019 | Feb 24, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 24, 2020 | Feb 24, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2020 | Feb 26, 2020 | — |
Addendum 15: Errcs-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 2, 2019 | Dec 2, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 2, 2019 | Jan 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2020 | Jan 13, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 13, 2020 | Jan 14, 2020 | — |
Addendum 16: Errcs-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 8, 2019 | Apr 8, 2019 | — |
Fire prevention review Fire Department · SFFD | Apr 8, 2019 | May 13, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 13, 2019 | May 13, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 13, 2019 | May 14, 2019 | — |
Addendum 17: Generator/fuel oil/piping-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 19, 2019 | Jul 19, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2019 | Aug 15, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2019 | Aug 16, 2019 | — |
Fire prevention review Fire Department · SFFD | Aug 16, 2019 | Nov 9, 2019 | — |
Building plan review Building Inspection · BLDG | Nov 4, 2019 | Nov 27, 2019 | — |
Permit Processing Center Building Inspection · PPC | Nov 4, 2019 | Nov 27, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2019 | Dec 2, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | — | Nov 27, 2019 | — |
Addendum 18: Generator/fuel oil/piping-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 20, 2019 | Aug 20, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 20, 2019 | Sep 13, 2019 | — |
Fire prevention review Fire Department · SFFD | Sep 13, 2019 | Sep 21, 2019 | — |
Permit Processing Center Building Inspection · PPC | Sep 23, 2019 | Sep 23, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2019 | Sep 25, 2019 | — |
Addendum 19: Bldg maintenance unit-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 1, 2019 | Mar 1, 2019 | — |
Building plan review Building Inspection · BLDG | Mar 1, 2019 | Mar 28, 2019 | — |
Permit Processing Center Building Inspection · PPC | Mar 28, 2019 | Mar 28, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Mar 28, 2019 | Mar 29, 2019 | — |
Addendum 20: Bldg maintenance unit-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 2, 2019 | May 2, 2019 | — |
Building plan review Building Inspection · BLDG | May 2, 2019 | Jun 25, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jun 25, 2019 | Jun 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jun 25, 2019 | Jun 27, 2019 | — |
Addendum 21: Bldg signage/off-site work-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 8, 2020 | Jan 8, 2020 | — |
Addendum 22: Bldg signage/off-site work-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 14, 2019 | May 14, 2019 | — |
Building plan review Building Inspection · BLDG | May 14, 2019 | Sep 13, 2019 | — |
Fire prevention review Fire Department · SFFD | Jun 26, 2019 | Apr 27, 2020 | — |
Permit Processing Center Building Inspection · PPC | Apr 29, 2020 | Apr 29, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Apr 29, 2020 | May 7, 2020 | — |
Addendum 23: Fsae-1500 mission
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 31, 2020 | Jan 31, 2020 | — |
Fire prevention review Fire Department · SFFD | Jan 31, 2020 | Feb 24, 2020 | — |
Permit Processing Center Building Inspection · PPC | Feb 25, 2020 | Feb 25, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2020 | Feb 27, 2020 | — |
Addendum 24: Fsae-49 so van ness
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 27, 2020 | Apr 27, 2020 | — |
Fire prevention review Fire Department · SFFD | Apr 27, 2020 | Jun 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | May 12, 2020 | May 13, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 3, 2020 | Jun 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2020 | Jun 4, 2020 | — |
Addendum 25: Arch-office interiors/structural (49 s. van ness)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 2, 2019 | Jul 2, 2019 | — |
Building plan review Building Inspection · BLDG | Jul 2, 2019 | Oct 1, 2019 | — |
Fire prevention review Fire Department · SFFD | Oct 1, 2019 | Oct 4, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2019 | Oct 4, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2019 | Oct 8, 2019 | — |
Addendum 26: Arch-child day care ctr (49 s. van ness)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 11, 2019 | Sep 11, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2019 | Dec 20, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2019 | Dec 23, 2019 | — |
Fire prevention review Fire Department · SFFD | Dec 23, 2019 | Apr 24, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2020 | Jan 23, 2020 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2020 | Jan 30, 2020 | — |
Permit Processing Center Building Inspection · PPC | Apr 24, 2020 | Apr 28, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Apr 28, 2020 | May 6, 2020 | — |
Addendum 27: Mep - office interiors (49 s. van ness)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 25, 2019 | Jun 25, 2019 | — |
Building plan review Building Inspection · BLDG | Jun 25, 2019 | Aug 15, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2019 | Nov 27, 2019 | — |
Electrical plan review Building Inspection · MECH-E | Sep 3, 2019 | Feb 6, 2020 | — |
Fire prevention review Fire Department · SFFD | Sep 30, 2019 | Mar 14, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 8, 2020 | Apr 8, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Apr 8, 2020 | Apr 8, 2020 | — |
Building plan review Building Inspection · BLDG | Apr 8, 2020 | Apr 23, 2020 | — |
Permit Processing Center Building Inspection · PPC | Apr 8, 2020 | Apr 24, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Apr 24, 2020 | May 6, 2020 | — |
Addendum 28: Mep-child day care ctr (49 s. van ness)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 14, 2020 | Jan 14, 2020 | — |
Building plan review Building Inspection · BLDG | Jan 14, 2020 | Feb 4, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 4, 2020 | Mar 12, 2020 | — |
Electrical plan review Building Inspection · MECH-E | Mar 31, 2020 | Jun 8, 2020 | — |
Fire prevention review Fire Department · SFFD | Apr 28, 2020 | Jun 10, 2020 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 4, 2020 | Jun 4, 2020 | — |
Building plan review Building Inspection · BLDG | Jun 10, 2020 | Jun 11, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 15, 2020 | Jun 15, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 15, 2020 | Jun 16, 2020 | — |
Addendum 29: Mid-block passage (1500 mission)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 5, 2019 | Sep 5, 2019 | — |
Building plan review Building Inspection · BLDG | Sep 5, 2019 | Dec 20, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2019 | Jan 2, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jan 3, 2020 | Jan 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2020 | Jan 7, 2020 | — |
Addendum 30: Greywater
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Feb 20, 2020 | Feb 20, 2020 | — |
Plumbing plan check Building Inspection · PID-PC | Feb 21, 2020 | Mar 3, 2020 | — |
Permit Processing Center Building Inspection · PPC | Mar 3, 2020 | Mar 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Mar 3, 2020 | Mar 13, 2020 | — |
Public health review Public Health · HEALTH | Mar 13, 2020 | Mar 13, 2020 | — |
Addendum 31: Off-site work/landscape
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 7, 2020 | Apr 7, 2020 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2020 | Jun 1, 2020 | — |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2020 | Jun 3, 2020 | — |
Permit Processing Center Building Inspection · PPC | Jun 3, 2020 | Jun 3, 2020 | — |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2020 | Jun 4, 2020 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $400,000,000
| Name | Role | License on permit |
|---|---|---|
| Clifton K Boswell Skidmore Owings&Merrill | Architect | C26963 |
| Brendan D Dunnigan Hks Architects | Architect | C28538 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025