1840 21st Av
San Francisco permit 201608034067 · Sunset/Parkside
Remodel of an (e) single family residence; addition of a new internal staircase; bathroom remodel, facade finishes and addition of a new deck
- Filed
- Aug 3, 2016
- Issued
- Jul 11, 2019 (35 months after filing)
- Completed
- Not completed yet
- Review stops
- 24 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 4, 2016 | Aug 4, 2016 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2016 | Aug 14, 2017 | — |
Building plan review Building Inspection · BLDG | Aug 15, 2017 | Sep 19, 2017 | — |
Permit Processing Center Building Inspection · PPC | Sep 19, 2017 | Oct 4, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2017 | Oct 12, 2017 | — |
Zoning review Planning · CP-ZOC | Oct 12, 2017 | Jan 3, 2019 | — |
Planning neighborhood notice Planning · CP-NP | Jul 16, 2018 | Dec 13, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 3, 2019 | Jan 15, 2019 | — |
Building plan review Building Inspection · BLDG | Jan 16, 2019 | Jan 24, 2019 | — |
Zoning review Planning · CP-ZOC | Jan 24, 2019 | Jan 31, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Feb 4, 2019 | Feb 7, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 8, 2019 | Feb 14, 2019 | — |
Building plan review Building Inspection · BLDG | Feb 14, 2019 | May 21, 2019 | — |
Zoning review Planning · CP-ZOC | May 21, 2019 | May 24, 2019 | — |
Permit Processing Center Building Inspection · PPC | May 30, 2019 | May 30, 2019 | — |
Central Permit Bureau Building Inspection · CPB | May 30, 2019 | Jul 11, 2019 | — |
Addendum 1: Arch,mech, t24, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 2, 2019 | Aug 2, 2019 | — |
Building plan review Building Inspection · BLDG | Aug 2, 2019 | Oct 10, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 27, 2019 | Oct 4, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2019 | Sep 16, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 17, 2019 | Sep 19, 2019 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 11, 2019 | Oct 15, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 15, 2019 | Oct 15, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 15, 2019 | Oct 23, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Bridgett R Shank Timbre Architecture | Architect | C32322 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021