125 Clement St

San Francisco permit 201608114830 · Inner Richmond

Commercial or tenant improvementFull plan reviewComplete
Street view · Feb 2025
Google Street View of 125 Clement St, Feb 2025
Scope of work
As written on the permit application.

Change of use.ti to(e)grd fl space.no wk on upper units.grd fl convert fr b-occupancy to e-occupancy.new space for children's daycare. (3) new bathrms will be created to replace exist (2) bathrms.create new exit corridor. (e)storefront will be modified for new exit.

Timeline
Key dates from the city record.
Filed
Aug 11, 2016
Issued
Apr 4, 2017 (8 months after filing)
Completed
Dec 5, 2017 (8 months after issuance)
City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
3 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 16, 2016—

Zoning review

Planning · CP-ZOC

Dec 8, 2016—

Planning neighborhood notice

Planning · CP-NP

Dec 8, 2016—

Building plan review

Building Inspection · BLDG

Feb 6, 2017—

Fire prevention review

Fire Department · SFFD

Mar 3, 2017—

Street use and mapping

Public Works · DPW-BSM

Jan 20, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

Feb 21, 2017—

Street use and mapping

Public Works · DPW-BSM

Mar 7, 2017—

Zoning review

Planning · CP-ZOC

Mar 14, 2017—

Permit Processing Center

Building Inspection · PPC

Mar 16, 2017—

Central Permit Bureau

Building Inspection · CPB

Apr 4, 2017—

Addendum 1: Arch,struct,t24, mech,final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 4, 2017—

Building plan review

Building Inspection · BLDG

Apr 10, 2017—

Structural plan approval

Building Inspection · PAD-STR

Apr 10, 2017—

Electrical plan review

Building Inspection · MECH-E

Apr 10, 2017—

Electrical plan review

Building Inspection · MECH-E

Apr 18, 2017—

Mechanical and energy plan review

Building Inspection · MECH

Apr 18, 2017—

Fire prevention review

Fire Department · SFFD

Apr 26, 2017—

Street use and mapping

Public Works · DPW-BSM

May 12, 2017—

Public Utilities Commission review

Public Utilities · SFPUC

May 16, 2017—

Permit Processing Center

Building Inspection · PPC

May 17, 2017—

Central Permit Bureau

Building Inspection · CPB

May 18, 2017—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$210,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Edward Stephan Kaplan

Kaplan Architects

ArchitectC12668
Sources