125 Clement St
San Francisco permit 201608114830 · Inner Richmond
Change of use.ti to(e)grd fl space.no wk on upper units.grd fl convert fr b-occupancy to e-occupancy.new space for children's daycare. (3) new bathrms will be created to replace exist (2) bathrms.create new exit corridor. (e)storefront will be modified for new exit.
- Filed
- Aug 11, 2016
- Issued
- Apr 4, 2017 (8 months after filing)
- Completed
- Dec 5, 2017 (8 months after issuance)
- Review stops
- 22 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 16, 2016 | Aug 16, 2016 | — |
Zoning review Planning · CP-ZOC | Aug 16, 2016 | Dec 8, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Oct 24, 2016 | Dec 8, 2016 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2016 | Feb 6, 2017 | — |
Fire prevention review Fire Department · SFFD | Jan 6, 2017 | Mar 3, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jan 18, 2017 | Jan 20, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 6, 2017 | Feb 21, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2017 | Mar 7, 2017 | — |
Zoning review Planning · CP-ZOC | Mar 9, 2017 | Mar 14, 2017 | — |
Permit Processing Center Building Inspection · PPC | Mar 16, 2017 | Mar 16, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Mar 16, 2017 | Apr 4, 2017 | — |
Addendum 1: Arch,struct,t24, mech,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 4, 2017 | Apr 4, 2017 | — |
Building plan review Building Inspection · BLDG | Apr 4, 2017 | Apr 10, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 5, 2017 | Apr 10, 2017 | — |
Electrical plan review Building Inspection · MECH-E | Apr 10, 2017 | Apr 10, 2017 | — |
Electrical plan review Building Inspection · MECH-E | Apr 18, 2017 | Apr 18, 2017 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 18, 2017 | Apr 18, 2017 | — |
Fire prevention review Fire Department · SFFD | Apr 18, 2017 | Apr 26, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2017 | May 12, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2017 | May 16, 2017 | — |
Permit Processing Center Building Inspection · PPC | May 16, 2017 | May 17, 2017 | — |
Central Permit Bureau Building Inspection · CPB | May 17, 2017 | May 18, 2017 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $210,000
| Name | Role | License on permit |
|---|---|---|
| Edward Stephan Kaplan Kaplan Architects | Architect | C12668 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025