1723 09th Av
San Francisco permit 201608165076 · Inner Sunset
Horizontal expansion . interior reovation. add a master bedroom & 1 bathroom. a total of 798 sf for both floors.
- Filed
- Aug 16, 2016
- Issued
- Dec 19, 2017 (16 months after filing)
- Completed
- Jan 24, 2020 (25 months after issuance)
- Review stops
- 18 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 6, 2016 | Sep 6, 2016 | — |
Zoning review Planning · CP-ZOC | Sep 6, 2016 | Jul 7, 2017 | — |
Planning neighborhood notice Planning · CP-NP | May 5, 2017 | Jul 7, 2017 | — |
Building plan review Building Inspection · BLDG | Jul 10, 2017 | Jul 24, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2017 | Aug 1, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 1, 2017 | Aug 14, 2017 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2017 | Aug 24, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Aug 24, 2017 | Dec 19, 2017 | — |
Addendum 1: Superstructure,t24,mech,ele,arh,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2017 | Dec 22, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 22, 2017 | May 24, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2018 | Mar 29, 2018 | — |
Structural plan approval Building Inspection · PAD-STR | Jan 22, 2018 | May 3, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2018 | May 29, 2018 | — |
Street use and mapping Public Works · DPW-BSM | May 24, 2018 | Jun 12, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 29, 2018 | May 30, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 14, 2018 | Jun 14, 2018 | — |
Permit Processing Center Building Inspection · PPC | Jun 14, 2018 | Jun 14, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Jun 14, 2018 | Jun 29, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $230,000
| Name | Role | License on permit |
|---|---|---|
| Chi-Wing Wong Collaborate Design Group | Architect | C-29630 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023