50 Surrey St
San Francisco permit 201610130162 · Glen Park
(front building) add single story,two car garage at front yard. two single rear yard addition. excavate basement level & refinish. interior alteration include renovation of kitchen, powder, basement bath 2nd floor bath. add 1 new bathroom at 2nd fl new dormers at roof. new interior stairs to replace
- Filed
- Oct 13, 2016
- Issued
- Oct 3, 2017 (12 months after filing)
- Completed
- Aug 8, 2022 (58 months after issuance)
- Review stops
- 28 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2016 | Oct 24, 2016 | — |
Zoning review Planning · CP-ZOC | Oct 24, 2016 | Apr 26, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Mar 2, 2017 | Apr 27, 2017 | — |
Building plan review Building Inspection · BLDG | Apr 27, 2017 | Jun 16, 2017 | — |
Street use and mapping Public Works · DPW-BSM | May 16, 2017 | May 31, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 1, 2017 | Jun 14, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2017 | Sep 19, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 20, 2017 | Oct 2, 2017 | — |
Development fee collection Building Inspection · DFCU | Oct 2, 2017 | Oct 2, 2017 | — |
Permit Processing Center Building Inspection · PPC | Oct 2, 2017 | Oct 2, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Oct 2, 2017 | Oct 3, 2017 | — |
Addendum 1: Slope protection act
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 27, 2017 | Nov 27, 2017 | — |
Building plan review Building Inspection · BLDG | Nov 27, 2017 | Aug 27, 2018 | — |
Permit Processing Center Building Inspection · PPC | Aug 28, 2018 | Aug 31, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2018 | Nov 5, 2019 | — |
Addendum 2: Structural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 10, 2018 | Sep 10, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 11, 2018 | Nov 15, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2018 | Nov 2, 2018 | — |
Permit Processing Center Building Inspection · PPC | Nov 16, 2018 | Nov 16, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Nov 16, 2018 | Nov 5, 2019 | — |
Addendum 3: Architectural/mechanical
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 24, 2018 | Oct 24, 2018 | — |
Building plan review Building Inspection · BLDG | Oct 24, 2018 | Dec 12, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Dec 3, 2018 | Dec 6, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2018 | Jan 9, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Jan 10, 2019 | Feb 8, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 10, 2019 | Feb 11, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Feb 11, 2019 | Nov 5, 2019 | — |
Addendum 4: Sprinkler
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 29, 2022 | Jul 29, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Cary S Bernstein Cary Bernstein Architecture | Architect | C27690 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025