172 Beaumont Av
San Francisco permit 201610140341 · Lone Mountain/USF
Gut renov&698 sf.rooftop addition at rear of(e)3,970 sf.(incl garage).2 story sfr. struct incl seismic upgrade,mech, elec/liteg&plumb wrk.(n)elevator,stair,replace(e)kitchen & replace 3 bathrms on 1/f&2/f;add 1 bathrm on top flr.cabinetry,flr,ceiling&wall finishes,rooftop deck,rear balcony &
- Filed
- Oct 14, 2016
- Issued
- Aug 22, 2017 (10 months after filing)
- Completed
- Not completed yet
- Review stops
- 16 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 25, 2016 | Oct 25, 2016 | — |
Zoning review Planning · CP-ZOC | Oct 25, 2016 | May 23, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Mar 20, 2017 | May 19, 2017 | — |
Building plan review Building Inspection · BLDG | May 24, 2017 | Jun 26, 2017 | — |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2017 | Jul 11, 2017 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2017 | Jul 28, 2017 | — |
Permit Processing Center Building Inspection · PPC | Jul 31, 2017 | Jul 31, 2017 | — |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2017 | Aug 22, 2017 | — |
Addendum 1: Superstructure,tl24,mech,ele,arch,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2017 | Oct 18, 2017 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2017 | Dec 8, 2017 | — |
Structural plan approval Building Inspection · PAD-STR | Dec 8, 2017 | Jan 30, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 30, 2018 | Apr 3, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Feb 20, 2018 | Feb 22, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2018 | Feb 27, 2018 | — |
Permit Processing Center Building Inspection · PPC | Apr 3, 2018 | Apr 3, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2018 | Aug 2, 2018 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $550,000
| Name | Role | License on permit |
|---|---|---|
| Kaveh Rad Kaveh Rad | Engineer | S3638 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025