333 Diamond St
San Francisco permit 201610271260 · Castro/Upper Market
Remodel of interior of (e) 2 unit bldg and (e) garage. development of (e) ground flr storage space as (n) bdrm & living room. rear addition for (n) family rm and master bdrm. (n) 4th flr for rec room study & bathroom.
- Filed
- Oct 27, 2016
- Issued
- Jun 7, 2018 (19 months after filing)
- Completed
- Oct 11, 2019 (16 months after issuance)
- Review stops
- 26 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 7 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 27, 2016 | Oct 27, 2016 | — |
Zoning review Planning · CP-ZOC | Oct 27, 2016 | Dec 8, 2017 | — |
Planning neighborhood notice Planning · CP-NP | Oct 25, 2017 | Dec 6, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 11, 2017 | Feb 22, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Jan 18, 2018 | Jan 22, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 23, 2018 | Feb 2, 2018 | — |
Permit Processing Center Building Inspection · PPC | Feb 22, 2018 | Feb 22, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Feb 22, 2018 | Apr 11, 2018 | — |
Zoning review Planning · CP-ZOC | Apr 11, 2018 | Apr 30, 2018 | — |
Building plan review Building Inspection · BLDG | May 1, 2018 | May 18, 2018 | — |
Street use and mapping Public Works · DPW-BSM | May 18, 2018 | May 22, 2018 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2018 | May 25, 2018 | — |
Permit Processing Center Building Inspection · PPC | May 25, 2018 | May 25, 2018 | — |
Central Permit Bureau Building Inspection · CPB | May 25, 2018 | Jun 7, 2018 | — |
Addendum 1: Foundation, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 20, 2018 | Jun 20, 2018 | — |
Building plan review Building Inspection · BLDG | Jun 21, 2018 | Sep 6, 2018 | — |
Permit Processing Center Building Inspection · PPC | Sep 6, 2018 | Sep 11, 2018 | — |
Central Permit Bureau Building Inspection · CPB | Sep 11, 2018 | Sep 11, 2018 | — |
Addendum 2: Architectural, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2018 | Sep 21, 2018 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2018 | Oct 22, 2018 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 22, 2018 | Dec 17, 2018 | — |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2018 | Jan 23, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 9, 2018 | Dec 18, 2018 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2019 | Jan 28, 2019 | — |
Permit Processing Center Building Inspection · PPC | Jan 25, 2019 | Jan 25, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Jan 28, 2019 | Jan 28, 2019 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,100,000
| Name | Role | License on permit |
|---|---|---|
| John S Winder Winder Gibson Architects | Architect | C13305 |
| My My Ly | Architect | C32972 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026