435 Alvarado St
San Francisco permit 201611223400 · Noe Valley
Renovate (e)(3)story over (1)basement single family. horizontal addition @ rear & vertical addition @ (e) attic @ 4th fl bedroom. upgrade bathrooms, kitchen & utilities including addition of a fire sprinkler system throughout (e) street facade to remain.
- Filed
- Nov 22, 2016
- Issued
- Apr 13, 2021 (53 months after filing)
- Completed
- Feb 3, 2025 (46 months after issuance)
- Review stops
- 17 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 5 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 23, 2016 | Nov 23, 2016 | — |
Zoning review Planning · CP-ZOC | Nov 23, 2016 | Dec 26, 2018 | — |
Fire prevention review Fire Department · SFFD | Nov 23, 2016 | Nov 23, 2016 | — |
Planning neighborhood notice Planning · CP-NP | Sep 22, 2017 | Nov 4, 2017 | — |
Building plan review Building Inspection · BLDG | Dec 27, 2018 | Oct 4, 2019 | — |
Street use and mapping Public Works · DPW-BSM | Mar 12, 2019 | Mar 13, 2019 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2019 | Sep 30, 2019 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2019 | Oct 4, 2019 | — |
Central Permit Bureau Building Inspection · CPB | Oct 4, 2019 | Apr 13, 2021 | — |
Addendum 1: Structural/archi/mep/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 20, 2021 | Apr 20, 2021 | — |
Permit Processing Center Building Inspection · PPC | Apr 20, 2021 | Jan 25, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 21, 2021 | Aug 4, 2021 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 29, 2021 | Nov 18, 2021 | — |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2021 | Jan 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2021 | Aug 26, 2021 | — |
Building plan review Building Inspection · BLDG | Nov 18, 2021 | Jan 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jan 25, 2022 | Feb 17, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,500,000
| Name | Role | License on permit |
|---|---|---|
| Sarah E Willmer Studio Sarah Willmer | Designer | C29126 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022